Recently, the reporter came to the construction site of the water conservancy facilities repair project in the Daliu River section of the Daqing River in Dongdian, Wen'an County, Langfang City, an excavator is cleaning up the soil and stone on the surface, and the vibration roller is compacting, the road section is 660 meters long and is expected to be completed in mid-December.

Shan Likun, project manager of the Water Conservancy and Hydropower Engineering Office of Guangyang District, Langfang City, told reporters that the wheat protection was washed away by the flood, causing many collapses, and after the flood, they quickly organized construction and repair.

Due to the narrow approach road in the early stage of construction, we adopted the method of flat road in front of the excavator, first cleared the surface, then carried out earthwork tamping, and then carried out earthwork backfilling, and the embankment body was restored, which will effectively protect the village and about 50,000 acres of farmland after completion. Shan Likun said.

The construction site of the water damage restoration project of the Daliu River section of the Daqing River in Dongdian. Photo by Wang Song, correspondent of the Great Wall Network Jiyun client.

The eastern part of Wen'an County is low-lying, known as Dongdian, and is one of the eight major depressions in Hebei Province. Eight of the four townships in the Dongdian Flood Storage and Detention Zone were hit by floods during this year's flood season, and some dams were damaged to varying degrees.

At the site of the water damage repair project in Toyo Town, Wen'an Prefecture, workers are pouring slurry masonry. The project is an important part of the Qianli Dike, which is a flood control barrier on the southern edge of the Daqing River Basin, which plays an important role in alleviating the flood control pressure and ensuring the safety of people's lives and property after the completion of the project.

Also located in the Dongdian Flood Storage and Detention Zone, Wen'an County Daqing River "Diversion into the Sea" North Gate Water Damage Repair Project is also going all out to catch up with the schedule, to ensure the construction period, the project has completed the hoisting of the new gate, the concrete pouring of the gate groove, and then dismantle the upstream and downstream cofferdams of the sluice.

Wen'an County Daqing River "Diversion into the Sea" North Gate Water Damage Restoration Project Site. Photo by Wang Song, correspondent of the Great Wall Network Jiyun client.

The North Gate Gate is an important passage connecting the Daqing River and the Zhaowangxin River, and the main project has been completed. In the future, when the flood in Dongdian is discharged, the flood water in Dongdian will be effectively prevented from entering the Zhaowangxin River to ensure the safety of flooding. Sun Saisai, project manager of Wen'an County Water Damage Restoration, said.

Wang Huatao, a member of the party group and a fourth-level chief staff member of the Wen'an County Water Affairs Bureau, said that the Wen'an County water damage restoration project has many long lines, tight time and heavy tasks. They dispatched relevant technical personnel to implement construction management of the project, and required each supervision unit to select business backbones to strengthen the supervision work. The construction units invert the construction period, wall chart operations, and make every effort to construct.

There are a total of 32 restoration projects for water-damaged water conservancy facilities in Langfang, of which 15 have started construction, all in Wen'an County. At present, the implementation of each project is progressing according to the time node. At the same time, fully prepare for winter construction, take necessary technical measures to ensure the quality of the project, and ensure that the construction task is completed with quality and quantity before the end of December.