After two years of overcoming difficulties and working overtime, the construction of Longgang Children's Park has been basically completed, and in order to ensure smooth operation, the park has recently carried out several rounds of testing work. Here, I would like to thank all the citizens for their continued support, attention and understanding. With the opening of the park imminent and the time being pressed, the park will no longer carry out large-scale testing and will focus on various sprint work for the opening of the park, including:
Carry out the final acceptance of the project.
Carry out the commissioning of facilities and venues.
Carry out traffic optimization and diversion work.
Carry out safety emergency response work.
Carry out communication network commissioning.
Carry out operational preparations and drills.
Aiming to open the park for trial operation at the end of December!
Tips. 1. In order to ensure safety, please be patient and do not enter the park without permission before the park opens.
2. In order to provide a more comfortable experience in the park, visitors will be able to make reservations to enter the park during the trial operation.
3. The parking spaces in the park are limited, please give priority to green travel, and self-driving citizens can go to the parking lots of the surrounding business districts, and we will also launch a traffic strategy in the near future.