On December 28, Henan Province's planned post-disaster reconstruction project of cultural relics Baiquan Spray Jade Pavilion, Lingyuan Pavilion, Yongjin Pavilion and Boat House was completed ahead of schedule in the ice and snow.
It is understood that since the start of construction, the "Santing Shiphouse" project has faced three major problems: the foundation reinforcement of flooded cultural relics, the ultra-short construction period to catch up with the work, and the extremely cold and freezing rescue repair. Huixian City Cultural Relics Protection Center to improve the political position, strict implementation of regulatory duties, anchor the Henan Province post-disaster reconstruction at the end of the year to complete the decisive battle goal, emergency deployment of special tasks, joint design, supervision, construction units cohesion, overcome difficulties, ahead of schedule to complete the post-disaster reconstruction tasks, to the provincial and municipal cultural relics departments, municipal party committees and all walks of life to hand in a satisfactory answer.
Overall planning and overall advancement. In accordance with the overall requirements of the post-disaster reconstruction effectiveness assessment, the provinces, cities and counties jointly carried out the special action of post-disaster reconstruction of cultural relics in Huixian County, organized on-site seminars, focused on goals, analyzed and judged, and provided a strong organizational guarantee for the promotion of the project. At the same time, Lv Junhui, former vice president of the Provincial Institute of Ancient Construction, Yu Xiaochuan, director of the Survey and Design Department, Lan Lizhi, professor-level senior engineer of Liaoning Nonferrous Metals Survey and Research Institute, and Hu Diming, chief of the Cultural Relics Management Section, were specially invited to set up an expert group to coordinate scheduling online and offline, and solve technical problems in the construction process in a timely manner.
Overall planning and coordination, full supervision. When the project started, the Huixian Cultural Relics Protection Center set the decisive goal of "fighting for 65 days and winning the battle for post-disaster reconstruction". Managers, division of labor and responsibility, work together. Technical personnel perform their duties and responsibilities, stick to the construction site day and night, and the project implements daily scheduling, daily meetings, and daily summary discussions, checklist assignments, and phased acceptance. Ensure the supervision of the whole process of the project and promote it with high quality.
Collaborate and implement efficiently. The city's design unit has repeatedly provided on-site guidance, cracked technical problems, and the supervision unit has always adhered to the site, keeping an eye on the quality of the project, avoiding overdue rework, and the construction unit has increased the number of construction personnel, reversed the construction period, and worked day and night, under the principle of adhering to the principle of "not changing the original state of cultural relics", it took the lead in completing the foundation reinforcement, wall repair, roof tile and other contents of the three cultural relics buildings of the jade pavilion, Lingyuan Pavilion and boat house. Yongjin Pavilion in the masonry wall, suffered for many years has not encountered minus 13 extremely cold weather, the Quartet unit immediately discussed and judged, reported to the expert group for instructions, formulated a response plan, adjusted construction measures, quickly erected insulation shed, increased warm facilities, the construction site outside the shed ice and snow, the shed is in full swing, work together to fight the cold winter, to ensure that the completion is completed on schedule.
Under the attention and scientific guidance of provincial, municipal and county leaders and experts, the participating units have overcome difficulties and coordinated operations to achieve the satisfactory results of the "acceleration" of the project and the "closing battle" with the decisive battle.