3 wind turbine manufacturers have entered the game, and the price of floating wind turbines has also

Mondo Gastronomy Updated on 2024-01-31

Polaris Wind Power Grid was informed that recently, the procurement of wind turbines for the prototype project of Hainan Wanning offshore floating project was announced. Standard package 1 and standard package 6 were won by CRRC Zhuzhou;Bid package 3 and bid package 4 were won by Dongfang Wind Power;Bid package 2 won the bid by Yunda shares;The winning bidder of the bid package 5 is electric wind power. It can be seen that the four winning bidders have the background of central state-owned enterprises, in addition to electric wind power, CRRC Zhuzhou Institute, Dongfang Wind Power, Yunda Co., Ltd. 3 companies do not have floating wind power prototype installation cases, this bid means that the above three wind power manufacturers officially entered the floating wind power market.

The first phase of the 100,000 kilowatt prototype project of PowerChina Wanning Floating Offshore Wind Power Pilot Project plans to install 6 wind turbines with a single capacity of 16MW-18MW, and each standard package corresponds to the installation of one floating wind turbine. According to relevant insiders, the bare machine part of the floating demonstration wind power project is within 3,000 yuan kw, and the lowest part has reached 2,700-2,800 yuan kw.

The cost of EPC unit kilowatts is 20,876 yuan

In June this year, the EPC general contracting results of the 100,000 kilowatt prototype project of the first phase of the Wanning floating offshore wind power pilot project were announced. The consortium composed of the joint leader of the Zhongnan Survey, Design and Research Institute of PowerChina and the Port and Shipping Construction of PowerChina, the Guizhou Engineering of PowerChina and the East China Survey, Design and Research Institute of PowerChina successfully won the bid.

The total number of winning bids for EPC general contracting is 208.8 billion yuan, equivalent to the EPC unit kilowatt cost of the project is 20,876 yuan (about 2.).10,000), judging from the EPC bidding below, the unit kilowatt cost of the ** is nearly 5,000 yuan lower than that of the second candidate.

Based on the overall EPC cost level of the floating wind power demonstration prototypes that have been completed and put into operation in China, the two prototypes that have been rolled off the domestic assembly line are between 38,000 and 40,000 yuan kilowatts. The EPC cost of the project has refreshed a new low in the industry.

The price of the fan under pressure conduction is reduced

The overall decline in EPC cost will undoubtedly transmit the pressure to the entire floating wind power project chain, but it is certain that once the demonstration project is completed and implemented on schedule with quality and quantity, it will lay a solid foundation for the commercialization of floating wind power projects in China in the future.

According to relevant insiders, the bare wind turbine of the floating demonstration wind power project is within 3,000 yuan kw, and the lowest has reached about 2,700 yuan.

However, only the decline of wind turbines is far from enough, and the cost composition of floating offshore wind power and fixed offshore wind power projects is different, with floating wind turbines accounting for only about 10% of the total cost, and construction and installation, mooring systems, and floating foundations accounting for more than 60% of the total cost. At present, the demonstration project has not yet been tendered for construction, installation, mooring system and other links.

New players enter the floating wind power sector

The floating wind market is huge, but how big is it?At present, there is no clear policy and specific planning document.

Relevant leaders of the National Energy Administration have said more than once this year that they will increase policy supply, improve systems and mechanisms, and introduce relevant policies for the development and construction of deep-sea offshore wind power as soon as possible in combination with the key tasks determined in the 14th Five-Year Plan for renewable energy development.

Before the introduction of relevant policies, major domestic mainstream machine manufacturers such as Mingyang Intelligent, China Haizhuang and Electric Wind Power have already laid out in the field of floating wind power.

In 2018, led by the Three Gorges Corporation and participated by South China University of Technology and Mingyang Intelligence, the first floating wind power R&D project in China was launched, and after three years, the Three Gorges "Leading" was successfully connected to the grid in Yangjiang, Guangdong.

In the same year, China Haizhuang obtained approval for its floating wind power project, which is located in the Zhanjiang Sea at a depth of 60 meters, and the prototype was successfully connected to the grid in 2022.

In 2022, the design plan of CNOOC's floating wind power project passed the group's review and construction began, and the project will be connected to the grid for power generation in 2023.

The construction of Goldwind's Wenzhou deep-sea base started in September 2022, with a total investment of 43 billion yuan, including a deep-sea floating R&D headquarters, a manufacturing and export base for offshore wind power large-capacity wind turbines, etc.

The first phase of the Wanning floating wind power demonstration project will be installed with three floating prototypes of CRRC Zhuzhou Institute, Dongfang Wind Power and Yunda Co., Ltd., and the prototype capacity is 16-18MW, which marks that there are three more powerful "players" in the field of floating wind power.