1. Construction preparation.

1.Clean up the site: Before construction, it is necessary to clean up the debris and garbage on the site to ensure the cleanliness and safety of the construction site.

2.Measurement and pay-off: According to the design drawings, use the measuring instrument to measure and pay off the floor, and determine the boundary and elevation of the floor.

3.Material preparation: According to the construction needs, prepare an appropriate amount of floor materials, such as concrete, mortar, etc., and ensure that the quality of the materials meets the requirements.

Second, the floor.

Dispose. 1.Ground leveling: For uneven ground, leveling treatment is required, and cement mortar or concrete can be used for leveling.

2.Floor cleaning: Before construction, it is necessary to use tools such as vacuum cleaners or mops to clean the ground to ensure that the ground is dry and tidy.

3. Construction of floor materials.

1.Concrete construction: For situations where concrete is required as a flooring material, concrete construction is required. In construction, it is necessary to pay attention to controlling the mix ratio and mixing quality of concrete, and ensure the compactness and flatness of concrete pouring.

2.Mortar construction: For situations where mortar needs to be used as a flooring material, mortar construction is required. In construction, it is necessary to pay attention to controlling the mix ratio and mixing quality of the mortar, and ensure the flatness and compactness of the mortar laying.

3.Special material construction: For the situation that requires the use of special materials as the floor, corresponding construction treatment is required. For example, the use of epoxy resins or wear-resistant and pressure-resistant materials requires corresponding construction according to the characteristics of the materials and the requirements of use.

Fourth, quality inspection and acceptance.

1.In the construction process, it is necessary to carry out quality inspection and supervision, and find and solve construction quality problems in a timely manner.

2.After the construction is completed, acceptance processing is required.

Workshop floor construction plan

1. Overview. The quality of the workshop floor has a crucial impact on the production efficiency and product quality of the workshop. A high-quality workshop floor not only improves production efficiency, but also ensures the safety and health of employees. Therefore, it is very necessary to develop a scientific and reasonable workshop floor construction plan. This program aims to provide comprehensive guidance on the construction of the workshop floor to ensure the quality and progress of the construction.

2. Preparation before construction.

Ground inspection: Conduct a detailed inspection of the workshop floor, and record the existing problems such as concave and convex, cracks, etc., so as to carry out ground treatment.

Clean the ground: Remove debris, oil stains, stains, etc. from the ground, and keep the ground clean and dry.

Determine the scope of construction: As needed, mark the construction area with chalk or paint to avoid exceeding the predetermined scope during construction.

Material preparation: According to the construction needs, prepare floor coatings, thinners, mortars and other materials to ensure the quality of materials.

Preparation of construction tools: Prepare construction tools such as roller brushes, scrapers, sandpaper, etc., to ensure that the tools are complete and in good condition.

3. Ground treatment.

Repair bumps: Use floor mortar or concrete to repair the bumps on the ground to ensure that the ground is flat.

Filling cracks: Filling cracks in the ground can be done with special crack repair materials to ensure that the ground is flat.

Grinding the ground: Use a grinder to grind the ground to remove surface impurities and improve the flatness of the ground.

Cleaning the floor: Rinse the floor with clean water to remove dust and impurities from grinding.

Dry the ground: Make sure the ground is completely dry so that you can proceed to the next step of construction.

Fourth, primer construction.

Primer blending: Mix the primer material and diluent according to the proportion of the primer instructions.

Primer coating: Use a roller brush to evenly apply the prepared primer to the workshop floor to ensure that the brush is evenly applied and there is no omission.

Dry primer: After the primer is applied, keep it well ventilated to allow the primer to dry naturally.

Check the primer: check whether the primer is uniform and flat, and repair it in time if there is any defect.

Fifth, the surface coating construction.

Mix the top coat: Mix the top coating material and the diluent according to the ratio of the instructions and stir evenly.

Brushing surface coating: Use a roller brush to evenly apply the prepared surface coating on the workshop floor to ensure that the coating is uniform and there is no omission.

Flattening the ground: After the surface coating is completed, use sandpaper to flatten the ground to improve the smoothness of the ground.

Dry topcoat: Maintain good ventilation to allow the topcoat to dry naturally.

Check the top coating: check whether the top coating is uniform, flat and smooth, and repair it in time if there is any defect.

6. Maintenance and maintenance.

Avoid hard objects: Avoid scratches on the ground with hard objects until the topcoat dries. If there are scratches, they should be repaired in time.

Avoid contamination: Avoid contaminants such as oil and water stains from touching the ground before the topcoat dries. If there is any pollution, it should be cleaned up in time.

Regular cleaning: Wipe down floors regularly with a mild detergent to keep them clean.

Regular inspection: Regularly check the flatness, smoothness and whether there are cracks on the ground, and deal with any abnormalities in time.

Maintenance & Maintenance: Follow the care and maintenance guidelines provided by the manufacturer to ensure that the floor is kept in good condition for a long time.

7. Precautions.

Construction personnel need to wear protective glasses, gloves and other protective equipment to ensure construction safety.

During the construction process, good ventilation should be maintained to avoid personnel inhaling harmful gases.

When blending coatings, the paint and thinner should be mixed according to the ratio of the instructions to avoid coating quality problems caused by improper proportions.

Related Pages