In November, a heavy snowstorm hit Tongliao City, Inner Mongolia Autonomous Region, with a maximum snowfall of 35 mm and a maximum snow depth of 25 cm. Schools are closed, airports are closed, ...... are closedPeople's production and life have been seriously affected.
Tongliao Country Garden i Shanghao Park project also ushered in the biggest test of this year's project promotion. Under the bad weather of rain and snow, the project team braved the wind and snow, faced difficulties, and went all out to ensure deliveryFinally, 234 houses were successfully delivered to the owners.
Tongliao is an extremely cold area, and due to the influence of bad weather, the road is covered with thick snow, vehicles cannot pass normally, and the traffic in the city is almost completely paralyzed.
Extreme weather has also brought many difficulties to the construction of the iShang Hao Park project: traffic obstruction has caused construction materials to be unable to be transported normally;The heavy snowfall caused some construction units to be unable to organize personnel to enter the construction site for construction operations. The project was at risk of being shut down, delayed, and not delivered.
Under the overall coordination of the person in charge, Shi Qinglei, every team of two people, each team is equipped with a car and a shovel to transport workers living in nearby villages and towns to and from the construction site every day to ensure the normal construction of the project every day. According to the engineering manager's recollection, "At that time, some roads were covered with deep snow, and the visibility was extremely low on snowy days, and there were many dangerous situations of slipping and skidding and snow stuck on the road to pick up and drop-off, but we did not have a single safety accident, and we can be said to have completed an impossible task." ”
After the personnel were in place, the shortage of on-site construction tools became the second problem in front of the project. The team members twisted into a rope, and the tools on the construction site borrowed each other, interspersed with use, and you used it again to make the construction efficiency as high as possible.
While the workers were in full swing with the construction work, other project members took shovels, snow shovels, brooms and other cleaning tools to carefully clear the snow on the roads and construction vehicles in the park under the heavy snowstorm to ensure the passage of workers and the entry of construction materials.
With the unremitting efforts of all members, the project finally completed the construction of the key line (indoor heating) on time, laying a solid foundation for the subsequent construction of other types of work and the realization of delivery.
In order to ensure that the house can be delivered to the owner at the agreed time, all members of the project will work hard to catch up with the project without violating the relevant regulations and not disturbing the people. Affected by factors such as long working hours, cold working environment, and high pressure on on-site coordination, the entire team was full of wounded soldiers before the project was delivered on November 30, but no one left the construction site. The project members who could not participate in the construction due to physical reasons also took the initiative to take on the task of preparing hot ginger water and purchasing medicines for everyone to support the delivery of the project.
Looking back on this period of time, Shi Qinglei, the project leader, said with emotion: "This is an unforgettable experience, we are fully committed to ensuring delivery, hoping to deliver the house smoothly to the owners and live up to the trust and expectations of the owners." ”
On November 30, after the unremitting efforts of the Country Garden i Shanghao Park project team, the fifth batch of 234 sets of the project began to be delivered.
For the owner, the delivery of each home is the beginning of a new life. On the day of delivery, the on-site staff was in place early, and all links worked together to guide the owners to sign in, review the data, handle the property services, and hand over the items from the reception area, the handling area to the rest area, so that the owners could smoothly receive the building.
Professional home inspectors provide one-to-one service, and the home inspectors also carefully record and give feedback to the needs and questions raised by the owners. Small problems are found to be dealt with in a timely manner, and civil engineering problems are reported to the owner on average for two days to report the maintenance progress. The property cooperates with the owner to open the water, electricity, gas and closed water test, and the property manager checks the leakage downstairs to avoid unnecessary losses. Wu Chen, the property housekeeper who served on site that day, has been checking the owner's information one by one and recording it, she said, "Record the actual situation of the owner, which is easy to check and more worry-free for follow-up services." ”
Ms. Li, the owner, praised the project and said: "It is really not easy, it was windy and snowy in those days, and it was difficult to travel, and we were also worried about whether we could receive the house on time. ”
Before taking over the house, the owner, Mr. Li, took the level and safety hammer to check every corner of the room many times, he said: "The indoor wall is smooth, the tiles are not hollow, I had worries before, now I am relieved, my family and I are more satisfied." ”
It is understood that Tongliao i Shanghao Park belongs to Country Garden North China, and since the development and construction of the project, it has strictly implemented the relevant national safety and quality standards for commercial housing, and won the honorary title of "Inner Mongolia Autonomous Region Construction Safety Standardization Demonstration Site" in 2021. Up to now, the project has delivered a total of 950 sets.