Illegal occupation of the sea was built before approval!The offshore wind company has been penalized

Mondo Social Updated on 2024-01-29

On December 13, the Natural Resources Bureau of Putian City, Fujian Province issued the "Administrative Penalty Decision (Putian Haixing Penalty No. 2023 003)".

According to the penalty decision, after investigation, Sanchuan Offshore Wind Power in Fujian Province will carry out the construction of Putian Pinghai Bay Offshore Wind Farm Area F in the sea area south of Nanri Town, Xiuyu District, Putian City from August 21, 2018Because part of the wind turbine foundations and submarine cables involved in the Putian Pinghai Bay Offshore Wind Farm Area F Project implemented by the company exceeded the scope of sea use specified in the sea area use warrant, it was an act of illegal occupation of sea area, in violation of the provisions of Article 3, Paragraph 2 of the Law of the People's Republic of China on the Management of the Utilization of Sea Space, the above acts are evidenced by evidence such as "On-site Records", "Inquiry Records", "Survey (Appraisal) Reports" and on-site **.

In accordance with Article 42 of the Law of the People's Republic of China on the Management of Sea Space Utilization, and the Notice of the Ministry of Finance and the State Oceanic Administration on Adjusting the Collection Standards for the Use of Sea Areas and Uninhabited Islands, this authority has decided to impose the following administrative penalties on Sanchuan Offshore Wind Power in Fujian Province

1.Order the return of illegally occupied sea areas;2.Restoration of the sea area to its original state;3.A fine of RMB 100,000,000,000,000,000,000,000,0 1444933 00,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,007)。

This is not the first time that Sanchuan offshore wind power in Fujian Province has been punished. On June 26 this year, the Putian Municipal Bureau of Natural Resources issued the "Administrative Penalty Decision on the Construction of the Submarine Cable Project of the Putian Shicheng Offshore Wind Farm Project without Approval in Sanchuan Offshore Wind Power in Fujian Province (Putian Natural Haixing Penalty No. 2023 002)" shows that the company has been in the company since June 8, 2019For the act of carrying out the construction of the submarine cable project of the Putian Shicheng Offshore Wind Farm Project without approval, in violation of the provisions of Article 3, Paragraph 2 of the Law of the People's Republic of China on the Management of the Utilization of Maritime Space, was punished:1.Order the return of illegally occupied sea areas;2.Restoration of the sea area to its original state;3.A fine of RMB 100 100 100 100 1864115 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 1032)。

In addition, on September 16, 2020, the administrative penalty decision of the Putian Municipal Bureau of Natural Resources (Putian Natural Sea Penalty No. 2020 001) showed that Sanchuan Offshore Wind Power in Fujian Province was issued from December 2019 to August 2020Illegal occupation of sea area for the construction of Shicheng offshore wind farm project without approval, in violation of the provisions of Article 3, Paragraph 2 of the Law of the People's Republic of China on the Management of the Utilization of Maritime Space, was punished:1.Order the return of the illegally occupied sea area and restore the sea area to its original state;2.A fine of RMB is 20,000 yuan (429897 yuan).

It is understood that the total investment of Putian Pinghai Bay Offshore Wind Farm Area F Project and Putian Shicheng Offshore Wind Farm Project is about 745 billion yuan, located in the southern sea area of Nanri Island and the northern sea area of Daitou Peninsula in Xiuyu District, Putian City, with a total construction scale of 400,000 kilowatts, which has been connected to the grid for power generation in July 2021. According to preliminary estimates, the average annual on-grid electricity after the completion of the above project is about 127.2 billion kWh.