Many people don't know much about the construction practice of basement floor warehouse joints, and here is an introduction related to this, which can be read and collected by interested family members and friends.
The construction of basement floor sub-warehouse joints refers to the division of different warehouse joints on the ground according to the design requirements and functional requirements in the process of basement floor laying, and the construction is carried out.
Design principles: 1. Determine the location and layout of the warehouse joints according to the use requirements and load requirements of the basement. Usually the warehouse joint can be divided into different areas according to the function of the floor, such as storage area, vehicle traffic area, pedestrian passage, etc. According to the functional requirements and load requirements of different areas, determine the position and width of the bin joint.
2.Arrange the shape and length of the warehouse seam reasonably. The shape of the warehouse joint can be straight, curved or polygonal, etc., and can be selected according to the actual situation and aesthetic requirements of the floor. The length of the warehouse joint should generally be determined according to factors such as the convenience of construction and the size of the covering material, so as to avoid the situation of being too long or too short.
3.Consider the waterproofing requirements of the basement. When designing the silo joint, it is necessary to pay attention to the waterproof requirements of the basement to avoid the problem of water seepage in the basement caused by the silo joint. Appropriate waterproofing materials or processes can be used to treat the silo joints to ensure the waterproofing performance of the basement floor.
Construction method: 1. Clean the surface of the floor. Before construction, the surface of the basement floor needs to be cleaned to ensure that the ground is flat and clean, and there is no debris or dirt.
2.Draw the bin seam line. According to the design requirements, the position and length of the silo seam are drawn on the floor using rope or ink lines.
3.Cutting the surface of the floor. Using a cutter or a hand-held chainsaw or other tools, cut according to the drawn silo seam lines to divide the basement floor into different areas.
4.Handling of silo seams. According to the design requirements, the cut bin seam is treated. You can use special caulk or caulk material to fill the joint to ensure that the connection between the joint and the floor is firm and flat.
5.Maintenance of floors. After the construction is completed, the basement floor needs to be cured to maintain the uniformity and aesthetics of its surface. During the maintenance period, it is necessary to pay attention to waterproof, dustproof and other measures to avoid damage to the floor.
Through the above design principles and construction methods, the construction of basement floor sub-warehouse joints can be effectively realized, so that it can meet the requirements of use and have good waterproof performance and aesthetics.