Stone curtain wall repair and reinforcement project

Mondo Social Updated on 2024-02-27

Hot Spot Engine Project Stone curtain wall repair and reinforcement project is an important project, which involves the safety and durability of the building. Stone curtain wall is a common exterior wall decoration material, but due to various reasons, it may be damaged and aged, and it needs to be repaired and reinforced. This article will introduce the characteristics and requirements of stone curtain wall maintenance and reinforcement engineering, as well as the precautions in the construction process. Characteristics and requirements of stone curtain wall maintenance and reinforcement project Stone curtain wall maintenance and reinforcement project has the following characteristics: 1Strong professionalism: The maintenance and reinforcement of stone curtain walls requires professional technology and knowledge, and the materials, structures and processes involved have their particularities. 2.High safety requirements: the maintenance and reinforcement construction of stone curtain wall is mostly carried out at high altitude, and necessary safety measures need to be taken to ensure the safety of construction personnel. 3.Difficult construction: Due to the installation location and structural characteristics of the stone curtain wall, many difficulties need to be overcome during construction, such as high-altitude work, narrow space, etc. 4.High quality requirements: The stone curtain wall after maintenance and reinforcement needs to meet the original design requirements to ensure the safety and durability of the building.

5.Cleaning and repairing stones: Cleaning the stones that need to be repaired and reinforced, removing dirt and loose parts, and repairing damaged parts.

6.Installation of reinforcing components: Install reinforcing components according to the design requirements to improve the bearing capacity and stability of the stone curtain wall.

7.Grouting and filling: grouting and filling the gaps and cavities of the stone curtain wall to ensure its compactness and waterproof performance.

8.Paste the stone slab: paste the cleaned and dried stone slab on the reinforcing member according to the design requirements to ensure its flatness and verticality.

9.Quality inspection and acceptance: Carry out quality inspection and acceptance of the repaired and reinforced stone curtain wall to ensure that it meets the original design requirements and quality standards.

10.Clean up the site: Clean up the construction site to make sure it's clean and safe.

During the construction process, the following matters need to be noted:

1.The construction is carried out in strict accordance with the construction plan and technical requirements to ensure the quality of construction.

2.Strengthen safety management and take necessary safety measures to prevent accidents.

3.Ensure that the construction site is clean and orderly, and prevent the impact on the surrounding environment and facilities.

4.Strengthen quality inspection and acceptance, and find and solve problems in a timely manner.