The reporter learned from the State Grid Fujian Electric Power Project that the last phase conductor of the 220 thousand volt Chicuo to Huatang line project was completed in Fuqing City, Fujian Province on January 26, and the overhead transmission line with the longest cross-sea distance in China was fully connected.
On January 26, the construction personnel of the State Grid Fujian Provincial Power Transmission and Transformation Project carried out the wiring operation at the construction site of the road. (Photo by Song Junling).
The Chicuo-Huatang line project is a connecting channel between Fuzhou Power Grid and the southeast clean energy hub, with a total length of about 30 kilometers and 23 overhead lines68 kilometers, 79 new towers, a total of 30 towers are located in the sea, the length of the sea is 14 kilometers.
In order to solve the problems of marine transportation and other problems, we have erected 47,000 square meters of trestle access, which can minimize the impact on the marine ecological environment compared to the traditional construction method of building sidewalks. Lian Yuqin, project manager of the construction project of the 220 thousand volt Chicuo to Huatang line project, said that the steel used for the trestle erection exceeded 56,000 tons.
It is understood that after the project is put into operation, it will not only meet the needs of regional industrial load development and improve the transmission capacity of offshore wind power, but also enhance the power supply capacity and reliability of the power grid in southern Fuzhou and Pingtan area.