Recently,Renmin Road East Extension ProjectSuccessfully completedZhangjiadun core block nine-year consistent school projectDelivered ahead of scheduleHangzhou Hanghai Road Gas Station (Comprehensive Energy Supply Service Station) ProjectPassed the acceptance of the five-party subject. Let's take a look!
no.1 Renmin Road East Extension Project was successfully completed
Renmin Road East Extension Project is located inTangqi Town, from Tangqi Road in the west to the junction of Donghu Street in the eastThe total length of the road is about 516 meters, and the width is 28 meters.
The main construction contents include roads, lighting, traffic signs, intelligent transportation, rain and sewage pipes, power pipelines and other supporting facilities.
Since the commencement of the project, the transportation group has actively coordinated with various line departments and local towns and streets, overcoming unfavorable factors such as the complexity of the original pipeline of the project and the difficulty of site relocationThe project was carried out as scheduled.
Recently,The construction of the project sign marking was completedIt marks the successful completion of the Renmin Road East Extension Project, which is one step closer to the completion and handover and opening to traffic, and also accelerates the progress of the regional transportation network east of Tangqi Road in the Tangqi Block.
no.2 The nine-year consistent school project in the core block of Zhangjiadun was delivered ahead of schedule
The nine-year consistent school project in the core block of Zhangjiadun is locatedTangqi Town, east of Chongchao Road, west of the planned commercial and residential land, north of Zhangjiadun Road for the planned residential land.
The total floor area is about59,000 square metersConstruction45 classesPedagogical scale.
for fitNine-year consistent system of sectional teachingAs a feature, the construction of a relatively independent green complex, reflected"Open, free and flexible".spatial characteristics.
At present, the physical construction of the project has been completedhandover, greening, traffic policeThe acceptance of other sub-items is progressing in an orderly manner, and the transportation group will continue to cooperate with itPreparations for the start of school in the spring.
no.3 Hangzhou Hanghai Road Gas Station (Comprehensive Energy Supply Service Station) project passed the acceptance of the five parties
The Hanghai Road gas station is located in QiaoSi Street, north to Kecheng Street, east to Hanghai Road green belt, west and south adjacent land boundary line,The site area is about 2,225 square meters.
The entrance to the gas station is set inOn Kecheng Street on the north side, the exit is set on Hanghai Road on the east sideThere are 6 sets of three-oil products and six-gun submersible pump type computerized tax-controlled refueling machines, with a total of 12 refueling spaces and 3 refueling channels, and refueling vehicles can smoothly arrive at the scheduled refueling parking spaces.
It is also set up in the station2 parking spaces for motor vehicles2 parking spaces for charging motor vehiclesIt was matched1 fast-charging charging pileto meet the needs of car owners for temporary parking and charging.
At present, the project hasPassed the acceptance of the five-party subject. The transportation group will speed up the acceptance work, strive to put into operation as soon as possible, and contribute to the improvement of the basic supporting facilities of the Qiaosi block and the improvement of the quality of urban functions.
In addition, the supporting road (Henger Road) project of Tangqi Loquat Park has been enteredFinishing stages,It is expected to beThe completion acceptance was completed in mid-January.
The projectFrom the east side of Shimu Port in the west (the intersection of Shimu Road and Henger Road), to Wangmei Road in the east;A new Sanguangang Bridge was built on Longitudinal 12th Road, and the road on the south side of the bridge was extended.
The total length of roads within the red line is approximate717 meters, the standard section is 18 meters wide. The main construction content includes road engineering, bridge engineering, pipeline engineering, lighting engineering, transportation facilities, landscaping and other ancillary projects.
After the completion of the project, the construction of the urban road network will be further improved"Meridians".Smoother.