The Gaoligongshan Tunnel of Dalui Railway is the first railway tunnel across the Hengduan Mountains in China, and the construction area has crossed 19 geological fault zones, covering almost all the poor geological conditions of tunnel construction, such as mud burst, water inrush, rockburst, and weak surrounding rock. On the eve of the Spring Festival, the reporter went deep into the underground construction site to experience the hardships and perseverance of the front-line builders.
The total length of the Gaoligong Mountain Tunnel is 345km, the maximum buried depth of more than 1,100 meters, is the Dalui railway project. In order to increase the working surface and speed up the construction progress, the China Railway Tunnel Bureau excavated the No. 1 shaft and the No. 2 shaft respectively 9 kilometers away from the entrance and 13 kilometers away from the exit. The shaft is a vertical tunnel connected to the tunnel excavated above the tunnel, which is the channel for tunnel construction to enter and exit slag, air circulation, and personnel to enter and exit. "Now that I've come to the No. 2 shaft of the Gaoligong Mountain Tunnel, I'm going to experience the super project buried deep in the "center of the earth" with the staff, let's go. "Reporter Lou Zhongxiang took us into the No. 2 shaft.
Shaft 2 has a vertical depth of 640 meters, which is equivalent to the height of a 200-story building. Under the leadership of Shao Linjiang, Minister of Engineering, the reporter walked into the special elevator tank for the first time and headed underground. Lou Zhongxiang: "I'll remember a time to see how long we went down to the bottom of the well, it is indeed a very deep shaft, my eardrum is uncomfortable during the descent, are we fast?" Shao Linjiang (Director of the Engineering Department of Shaft 2 of the Gaoligongshan Tunnel): "The speed of the tank is three meters per second, and under this high speed, the eardrum will produce an imbalance in air pressure. When we first came, we also experienced insomnia because of this situation. ”
As the elevator continued to descend, it was pitch black all around, but the sound of water in the ears was getting louder and louder, and through the faint flashlight, the reporter saw that the seepage of the well wall was getting bigger and bigger. "How did you feel when you first went down the mine? "There is still a sense of fear in such a deep shaft, and in such a dark and claustrophobic space. "It's almost five minutes now, and I can see the construction scene at the bottom of the well. ”
After about 6 minutes of travel, the reporter reached the bottom of the well. The construction area is crisscrossed by roadways, and Shao Linjiang, minister of engineering, told reporters that there are more than 15,000 square meters here, the size of 35 basketball courts, and more than 30 machines are started at the same time in 8 working faces every day. Due to the need to cross 16 extrusion and crushing zones in the construction area, the main tunnel has only been excavated for more than 240 meters, which is extremely difficult to construct. Shao Linjiang: "I'll give you a unique performance, called 'hand-digging granite'." Lou Zhongxiang: "These will be dropped as soon as they are buttoned." Shao Linjiang: "Yes, these are the granites that have been weathered and turned into mud when exposed to water. If such a situation is encountered during the excavation process, it is easy to cause the tunnel face to collapse. ”
Shaft 2 runs through seven aquifers, and the weak surrounding rock is often accompanied by mud inrushes and water inflows, with a maximum water pressure of 7 megapascals, equivalent to 700 meters of water. "Waterfall overhead and pedal stream" is the norm of underground construction. In such an environment, more than 600 slag slag needs to be transported to the surface through the bottom of the shaft slag transfer system every day, and a hooker needs to pull a one-ton hook by hand an average of 60 times a day. At the bottom of the No. 2 shaft, reporter Lou Zhongxiang learned the details of the daily work from Libin, the hook project: "It's just that the water is big, you see." "Do you get wet when you get back from work?" "It's all damp inside anyway. ”
In a blink of an eye, it was lunch time, and the food was delivered from 600 meters of ground, and it was the most relaxing time for everyone to eat. Li Lujin, a driller and blaster, put down the 60-kilogram wind drill and said with a relaxed face: "'Tunnel tunnel, on call', it does not have a regular time to go to and from work, it is on call 24 hours a day, no matter day or night, even in the middle of the night to notify you to come." ”
The maximum water inflow from Well No. 2 reached 140 cubic meters per hour, far exceeding the safe water output. In the underground pumping room at a depth of 640 meters, seven high-power centrifugal pumps are on standby. Pumping worker Xu **'s hometown is far away in Jiayuguan, Gansu Province, and he and another colleague stick to this post all year round. This year's Spring Festival will be the eighth year that he has not gone home for the New Year. Reporter Lou Zhongxiang talked with the pumping worker Xu **: "Home, I don't have any big wishes, I just hope to go back often to accompany my children and old mothers, just like others, the family is there when I eat." "That's what you want? "Yes. "Thank you, thank you for your hard work. ”
Reporter's Notes
During the two days of the interview, I sighed more than once"It's not easy", this group of ordinary laborers simply replied"For the sake of life""Proud of this tunnel"。I would say that when they come, they are separated by mountains, but when they go, they are sure to go"Tunnels"Through the mountains and rivers, the road leads to the world"The tunnel is also very proud of them"。
*: Baoshan Radio and Television Station Ren Xiaoming, Lou Zhongxiang, Xiao Yuanxing |Correspondent Xiong Daxiao Wan.
Editor: Jiang Yonghua Responsible Editor: Yang QingzongAbout Baoshan News Network
The WeChat is managed by the Baoshan News Network of the Propaganda Department of the Baoshan Municipal Committee of the Communist Party of China, and is an authoritative new publishing platform in Baoshan City. Follow this account, you will be able to receive Baoshan news information in time. All rights reserved,**Please indicate the source!
Baoshan News Network contact information
WeChat with the same number) Submission email: wx@bsxwcn