Drinking water safety is linked to people's livelihood and well-being, and social development. Since the launch of the second batch of theme education, Longmen County has done a good job in people's livelihood, vigorously promoted the optimization of the drinking water and water environment for the masses, accelerated the integration of urban and rural water supply in Longmen, and improved the quality of life of residents.
The main water supply network of Luxi was opened in mid-November last year
Longmen County has made great efforts to solve the problem of safe drinking water for the masses and vigorously promoted the construction of centralized water supply projects. The project mainly includes two parts: one is the expansion and quality improvement construction project of Longmen County Water Plant, including the construction project of the second water source raw water pipe of Longmen County Water Plant, the upgrading and reconstruction construction project of Longmen County Water Plant and the construction of water supply pipe network in Luxi area of Longjiang Town, Longmen County; The second is the rural centralized water supply project in Longmen County.
The water supply pipe network construction project in Luxi area, Longjiang Town, Longmen County is one of the sub-projects of the expansion and quality improvement construction project of Longmen County Water Plant. At present, the project has been fully completed in November last year and smoothly opened to water, which also marks that the residents of Luxi area can share the same water source, the same pipe network, and the same water supply as the people in the county water plant in the future, and ensure that the three elements of "water pressure, water quantity, and water quality" meet the standards.
The county water plant realizes dual water source water supply
Previously, the Baisha River Reservoir, as the only source of drinking water in Longmen County, could no longer meet the future water demand. Longmen County vigorously promotes the construction of the second water source raw water pipeline project of the county water plant to solve the growing contradiction between supply and demand of water for the masses.
The construction project of the second water source raw water pipeline of Longmen County Water Plant is a new one with a total length of 1106 kilometers of water pipelines, with a water transmission capacity of 160,000 tons per day. The water pipeline is connected with the water connection of the Tiantianshan Reservoir Dam, and the high-quality raw water of the Tiantianshan Reservoir is transported to the county water plant, and together with the water supply pipeline of the Baishahe Reservoir, it is treated to form high-quality drinking water and flow into the homes of the people of Longmen.
The estimated total investment of the second water source raw water pipeline construction project of Longmen County Water Plant is 20.2 billion yuan, the project was completed at the end of last year. At present, Longmen has formed a dual-water supply pattern of Tiantianshan Reservoir and Baishahe Reservoir. Chen Zhiwen, deputy general manager of Longmen County Water Affairs, said.
The county water plant upgrading project is scheduled to be completed by the end of April
The county water plant upgrading and reconstruction construction project is one of the sub-projects of the Longmen county water plant expansion and quality improvement construction project. Since the implementation of the project, Longmen County Water Affairs has taken multiple measures to promote the construction of the project, so that 'safe water' and 'happy water' can flow into people's homes. Chen Zhiwen said that the construction content of the project includes the transformation of the No. 1 production line of the county water plant, the transformation of the flocculation reaction tank of the No. 2 production line, the construction of a new set of simple dewatering equipment for sludge discharge, the increase in the turbidity of the inlet and outlet water of the filter on Line 1, the first testing facility for water supply HP and residual chlorine, and the construction of a new clear water pool.
The reporter learned that the total investment of the Longmen County Water Plant Upgrading and Construction Project is estimated to be 39.49 million yuan, and the project is expected to be completed at the end of April this year.
Huizhou ** reporter Huang Yuxiang.