The heavy rain on 23.7 "caused water accumulation and serious damage to the road. Beijing Youth Daily reporter learned that the Fangshan Highway Branch actively did a good job in road rescue and disaster relief, and after the unremitting efforts in the stage of rushing through and protecting the pass, as of the Spring Festival, the Fangshan District Water Damage Restoration Project has completed the repair of 37 roads. At present, the flood damage restoration project in Fangshan District has all resumed work and production, and all 17 roads are in place.
It is understood that after the heavy rain disaster, as of August 19, 2023, 54 water-damaged roads above the county level in the region have reached the social vehicle traffic standard.
On September 30, 2023, the Fangshan Highway Branch was responsible for a total of 44 projects and 54 roads for the post-disaster recovery and reconstruction projects of highways above the county level, with a total mileage of 821 kilometers and a repair mileage of 238 kilometers, including 63 bridges, and the Fangshan District Water Damage Restoration Project was officially started. All participating units worked overtime and worked at full speed to do a good job in the construction of the water damage restoration project. Fangshan District has invested more than 6,100 people per day on average, more than 1,100 sets of machinery, and in the road restoration and reconstruction construction, the sub-bureau requires the participating units to adopt sprinkler water and dust reduction, filter screen coverage, off-peak construction, night construction, etc., to overcome the difficulties of tight construction period and high traffic pressure, and strive for the best balance between construction and road traffic capacity to ensure that the impact on the masses is minimized.
As of the Spring Festival, the Fangshan District Water Damage Restoration Project has completed the repair of 37 roads, and the investment has been completed 14200 million yuan, accounting for 22% of the total investment63% of $5.8 billion. The remaining 17 roads are mainly used for bridge construction, steel plate guardrail construction, part of the stone concrete retaining wall construction and road area environmental improvement.
During the Spring Festival, all participating units are required to continue to make preparations for the resumption of work, and the management personnel continue to deepen the study of the construction plan, prepare various construction details, and insist on making the workers' resident and internal information practical and detailed, so as to provide good conditions for the resumption of work after the holiday. The construction and management personnel of each project are ready to resume work at any time, adhere to the premise of ensuring the quality of winter construction, continue to deal with various construction details in the conditional road sections, and make various preparations for large-scale construction after the holiday.
At present, the Fangshan District water damage restoration project has all resumed work and production, and all 17 roads are ready in place. Ensure that all projects are completed before the flood season this year.
In the next step, the Fangshan Highway Branch will further increase the investment in personnel and machinery, urge all participating units and departments to continue to work at full speed, and seize the time node in accordance with the overall requirements of Beijing's "basic recovery in one year, comprehensive improvement in three years, and long-term high-quality development".
Text: Beijing Youth Daily reporter Ye Wan.