Pass the assessment!Metro Line 19 will open soon

Mondo Social Updated on 2024-01-30

Wuhan Evening News, December 20 On December 20, the four-day pre-operation safety assessment meeting of Wuhan Rail Transit Line 19 project was successfully concluded, and the adjustment project of Line 19 successfully passed the initial pre-operation safety assessment, marking that the line has the initial operation and opening conditions and is about to be opened.

Line 19 train. Photo by correspondent Yuan Yonghua.

From the 17th to the 20th, 18 technical experts in the rail transit industry conducted a strict review of the basic conditions before the initial operation of the Line 19 project. The review was divided into 5 groups: the overall group, the civil engineering group, the equipment group, the equipment group, and the operation group.

Line 19 Wuhan Station West Square Station. Photo by correspondent Yuan Yonghua.

The expert group believes that the safety assessment work before the initial operation of the Line 19 project is well prepared, and generally gives high praise. At present, the system joint debugging has been completed, and the professional indicators such as vehicles, power supply, signals, and electromechanical equipment meet the national standards, and have the technical ability and professional level of normal operation.

Line 19 Huashan Xincheng Station. Photo by correspondent Yuan Yonghua.

The total length of Wuhan Rail Transit Line 19 is about 233 kilometers, all underground lines, set up 7 stations, the line project starts from Wuhan Station West Square Station, along Wudong Road, Huacheng Avenue, Huashan Avenue, Optics Valley 5th Road, and ends at Crescent Creek Park Station.

The initial pre-operation safety assessment is a comprehensive inspection and scientific evaluation of the operating conditions of the rail transit project for opening and carrying passengers. Wuhan Metro Group will organize all departments and participating units to further rectify and improve in strict accordance with expert opinions, and complete the initial operation of the reporting and approval process in accordance with relevant regulations, so as to realize the opening and operation of the line as soon as possible.

Reporter Tao Changning, correspondent Zeng Si, Yuan Yonghua).

Editor: Yu Lina].