The bridge is stable, and it is safe to walk on it!"Recently, it is located in the west section of Binchuan Road, Jiangchuan Road StreetGreen BridgeIn only 45 days, the repair was completed and normal traffic was restored, supporting the stable happiness of the elderly in the surrounding communities
It is reported that the Green Bridge was built in 1989, with a length of 26 meters and a total width of 6 meters5 meters, is the city's first continuous overall planning of the aging renovation projectThe central coordinates of the "One Bridge and Four Directions" Aging Transformation Demonstration Base
The southeast, northeast, southwest and northwest directions of the bridge are respectively built with barrier-free trails, community canteens, activity rooms for the elderly, community comprehensive service centers for the elderly and elderly care homesIt is a "people's bridge" that connects embedded elderly care service facilities and solves the problem of eating, caring for the elderly and entertainment.
Before the repair, there were many dark wounds on the green bridge slab girder, pier abutment and bridge deck
In the early stage, the professional department tested, the green bridge due to the long construction time, the frequency of use is high, the bridge plate beam, pier abutment, bridge deck, railing and other parts of the bridge have different degrees of cracks, subsidence and other diseases, there are certain safety hazards, repair is imperative.
In this regard, Jiangchuan Road Street attaches great importance to the inclusion of the green bridge repair in the theme education as one of the important tasks for the private sector, so as to ensure the safe passage of personnel while shortening the construction period as much as possible and minimizing the impact.
The Green Bridge after the restoration
In early October this year, the street combined with the actual situation and asked the design unit to formulate a detailed construction plan. Engineering adoptionThe way in which the whole half-width partition is constructedThis method not only achieves the safe passage of personnel, but also shortens the construction period by nearly half a month, greatly reducing the inconvenience to residents.
Bridge deck paving, concrete repair, crack repair, railing replacement, ......After repair, the green bridge not only improves the appearance of the bridge, but also further improves the bearing capacity of the bridge, complements the surrounding pension service facilities, and jointly supports the stable happiness of the elderly.
Editor: Qin Congcong.
Contributed by Jiang Xiaochuan.