Six steps to build a new energy charging station internal information .

Mondo Cars Updated on 2024-01-19

First, preparations.

Site selection:

1.The site is selected in a parking space or a green parking space.

2.Parking spaces should not be too tight, and external vehicles should be supported.

3.Business districts, high-speed rail stations, and railway stations are preferred.

4.The entrance and exit of the parking space is convenient to avoid congestion.

Venue Signing:

1.Land certificate or lease contract for the site.

2.The business license, legal person seal and legal person of both parties.

3.The contract seal or personal seal of both parties.

4.A legal and compliant venue contract for the site.

5.It is necessary to provide the floor plan of the site, the Red Warp Section, the building.

2. Filing

1.The ** number of the registration of the legal entity's ID card.

2.Legal entity ID card.

3.The company unifies social credit**.

4.The detailed address of the site, the number of charging piles, and the cost planning.

Third, land review

After obtaining the record certificate, go to the Land and Resources Bureau to carry out the ownership of soil and property rights.

Fourth, planning review

After clarifying the legality of the land, we went to the planning bureau to do a land use review and determined that there was no other plan for the site in the next few years.

5. Electricity declaration

1.Calculate the capacity of the transformer

2.The person in charge of the project shall fill in the application form, the letter of request, the copy of the project approval document, the copy of the plant floor plan, the original and copy of the applicant's ID card, the copy of the business, the land use certificate, etc.).

3.The power supply company conducted an on-site survey a week later and determined that the supply would be 30 working days for the high-voltage dual power supply to supply power

4.The design unit with design qualifications entrusted by the enterprise itself Materials (power supply scheme reply form, design power of attorney, design drawings must be sent to the power supply company for review and qualification, out of the material procurement and engineering construction, otherwise the power supply company will not

5.The company pays the fee

6.The enterprise shall organize its own bidding and procurement in line with the industry and position qualification for construction, and the qualification certification materials shall be required before construction

1) The product qualification manual of the equipment.

2) Acceptance records, installation technical records (including hidden.

3) As-built drawings, construction instructions (construction technology.

4) The electrical department with the audit opinion of the power supply company is designed.

5) The information and records that the power supply enterprise deems necessary.

6) The as-built drawings of the electrical part are 1 after the power transmission of the project.

Sixth, acceptance confirmation

After the construction is completed, the power company will carry out acceptance, including identification, signboards, fire-fighting equipment, etc., and power on after acceptance, and then the charging pile will be tested by a third-party testing agency, and a test report will be issued, and it can be put into operation after completion.

If you have land resources in your hand and want to build a new energy charging station, please contact us Tuxing Technology: 186-3814-6618 Tuxing charging pile integrates R&D and production. More than 30 cities across the country have experience in building stations and have been in-depth cooperation with Jiangxi Tower Group!Choose us to make money with confidence!