TSG51-2023 refers to the "Safety Technical Regulations for Lifting Machinery", which is a large specification and inspection regulations, which involves several major aspects of lifting machinery, such as manufacturing, design, inspection, etc.
According to Announcement No. 20 of 2023 issued by the State Administration for Market Regulation, the regulation (TSG51) will be officially implemented on January 1, 2024. That is, after this New Year's Day holiday, it will be officially implemented.
It is believed that in the early stage, all inspection agencies have formulated inspection records, inspection reports, work instructions, and detailed rules for filling in the original records of lifting machinery in accordance with the relevant requirements of TSG51-2023. In the near future, the final publicity and implementation training should be carried out before implementation.
The new safety technical specifications for lifting machinery are very different from the old ones。For example, metallurgical cranes, wireless remote control devices, and so on. The early electric single girder for lifting molten metal has no corresponding category in the new safety technical specifications, only "metallurgical crane".
It needs to be reminded here that according to the General Administration's "Notice on Issues Concerning the Implementation of the "Safety Technical Regulations for Lifting Machinery":
First, on the mechanical parking equipment installation of overload limiters,Some common mechanical parking equipment can be installed without an overload limiter.
For multi-layer circulation, roadway stacking, plane moving, vertical lifting and automobile special lifting mechanical parking equipment, it shall be in accordance with regulation a 512(5) requires the installation of an overload limiter. For simple lifting, lifting and traversing, horizontal circulation and vertical circulation mechanical parking equipment, it is not required to install an overload limiter for the time being. For this type of mechanical parking equipment, it should be a common mechanical parking equipment in major hospital parking lots, shopping mall parking lots and other areas.
2. On the implementation of the first inspection of the lifting machinery installation notice.
Procedure 64.1 (3) stipulates: For the lifting machinery inspected for the first time, whether it is installed by the user unit itself or entrusted to the installation unit, the user shall go through the installation notification procedures. The General Administration's "Notice on Issues Concerning the Implementation of the "Technical Regulations for the Safety of Lifting Machinery" stipulates that in accordance with the regulations 64.1 (3) When the installation is notifiedThe installation unit shall inform the hoisting machinery that has an installation process, and there is no need to inform the hoisting machinery that does not have an installation processThat is, either it will be informed by the installation unit, or it will not need to be informed. There is no need to be notified by the user.
The main types of cranes that will be inspected for the first time in TSG51-2023 are: 1. Electric single-girder cranes in overhead cranes(Do I need to install it?))2. All varieties of mobile cranes: tire cranes, crawler cranes, container reach stacker cranes, railway cranes. 3. Cable crane 4, mast crane 5, rail-mounted container gantry crane, rubber tyred container gantry crane, shore container crane, loading and unloading bridge in the form of ro-ro of the whole machine.