At the end of the year, the construction site of Mengguan Expressway of China Railway 15th Bureau and a company was in full swing, and the sound of welding and cutting came and went, and there was a boom of "rolling up your sleeves and working hard" everywhere.
The project is located in the ** zone, and nearly half of the year is the rainy season. Zhang Bo, the person in charge of the Mengguan project of the first company of the 15th Bureau of China Railway, said, "The fourth quarter is the first period of construction, and we must race against time to recover the delayed construction period!."”
Since October, the project has closely focused on the goal of "decisive battle in the fourth quarter and decisive victory in the coming year", and has taken multiple measures to carry out all-out tackling and strongly promote the construction progress of the project.
The business department strengthens the guarantee of elements, takes the initiative to provide front-line services, establishes a work group that directly connects with the scene, and promotes the solution of problems and difficulties in the first time, so that problems do not stay overnight, contradictions are not let go, and improvements are not stopped, so as to consolidate rear support. The project firmly establishes the concept of "lean construction runs through the whole life cycle of the project", adheres to the standardization of process control, grasps each process with a rigorous attitude, and achieves the ultimate in quality management. Safety can not be ignored, the project has consistently paid close attention to the implementation of responsibilities, strengthened risk control and hidden danger investigation and rectification, strictly implemented 24-hour duty and "leadership with shift system", in-depth implementation of safety standardization, and made every effort to ensure the safety of all aspects of construction.
The environment where the project is located is humid, and ordinary steel formwork is very easy to rust, so we have purchased '5+1' stainless steel formwork for this characteristic. Xing Keqiang, the chief engineer of the project, introduced that in the beam field, the finished box girders are neatly arranged, the pieces are beautiful inside and outside, and the mirror effect is remarkable.
In addition, the ratio of bridges and tunnels of the project exceeds 60%, the amount of cement, sand and gravel is large, and the line is adjacent to the tributaries of the Lancang River, an international river, so environmental protection work is equally important. Xing Keqiang introduced that in order to solve the problem of wastewater and dust, the project took the initiative to use scientific and technological innovation for daily management, environmental protection filter treatment system, so that turbid wastewater can regain "innocence" and truly "zero discharge and full reuse".The spray system of the washing machine and the silo makes the dust "nowhere to hide", helping the construction and production to be environmentally friendly and more efficient.
Up to now, the project has completed 60% of the overall image project progress. Zhang Bo said, "We will seize the favorable weather, reverse the construction period, continue to make efforts, unswervingly promote production in accordance with the established planning and deployment, and promote the big dry boom to heat up and speed up again." ”
Yunnan Net reporter Li Chenghan correspondent Huang Jie.