21 How do you eliminate the waste of waiting?
Answer: Adjust the division of labor and strictly organize production.
22 How to eliminate waste in the handling process?
Answer: Adjust the layout and organize the logistics reasonably.
23 How to eliminate wasteful movements?
Answer: Improve the station layout and operation method to reduce the waste of action.
24 What is "pull-in" production?
Answer: the so-called "pull" production is that the production of each process is pulled by the needs of the next process, what to produce, how much to produce, when to produce are to meet the needs of the next process premise.
25 What is the "three-for-the-system" in the lean production mode?
Answer: The so-called "three-for-system" is to take the production site as the center, the production workers as the main body, and the workshop director as the head.
26 What is the group work method?
Answer: The group work method means that the production organization of the enterprise takes the group as the unit, not only organizes production, but also participates in management and even operation.
27。What are the responsibilities of the group in the "group work method"?
Answer: Complete the production task, ensure product quality, control material consumption, replace and adjust the tooling and fixture, do a good job in equipment maintenance, and engage in on-site improvement.
28 What are the four main contents of the on-site operation standard?
Answer: The main content of the operation standard includes four aspects: production cycle, standard work-in-progress, process procedures and quality.
29 What is the relationship between "5S" activities and lean production methods?
Answer: "5S" activities are the basis of all management work, and if you do not do "5S" activities, it can only be an empty word to implement lean production methods.
30 Is the operation standard in the lean production method formulated by the on-site management personnel (or functional departments) or by the production team leader?Where should the job be hung?
Answer: It is mainly formulated by the production team leader, and should be hung on the job site at the same time.