The beam yard of Mingji Expressway 1 1 work area successfully completed the prefabrication task

Mondo Military Updated on 2024-01-29

On December 12, with the completion of the pouring of the last concrete, the prefabrication task of the box girder in the beam yard of the 1-1 work area of Mingji Expressway was completed, laying a solid foundation for the subsequent beam penetration.

The beam yard of the 1-1 work area of Mingji Expressway undertakes the work of 1350 pieces of prefabricated box girders, including 1028 pieces in the 1st work area and 322 pieces in the 2nd work area. In order to ensure that the prefabricated production of box girders can form a flow operation, and ensure that there is enough space to store prefabricated box girders in the beam storage area, the project department has attached great importance to the prerequisites such as the construction of the beam yard site and the production line since the start of construction. The division of labor between the formwork installation and the pouring of concrete is clear, and the factory operation and streamlined management are realizedIn addition, the beam yard is also equipped with solid management personnel and technical force, and the technical personnel with rich experience in beam-making technology are dispatched to carry out on-site technical guidance and process control, strictly implement the construction specifications and standardization requirements for control, and strictly implement the three-inspection system to ensure that the production of beams is beautiful inside and outside, and the dimensions are standardized, and the whole process control from point to surface is carried out, so that the beam-making task can be completed quickly, with high quality and efficiency.

At present, in addition to the completion of the prefabricated box girder work of the project department, other projects are steadily advancing, all the employees involved in the construction of our work area continue to carry forward the spirit of tenacious struggle, overcoming difficulties, and striving for the first project construction, and constantly strengthen the training of construction personnel at the professional level, actively integrate effective resources, optimize the construction plan, pursue excellent management, and strive to build high-quality projects.

100 help plan

Related Pages