In the early morning of December 29, the traffic function improvement project of the S4 highway into the city section (Xinzhuang Interchange - Jindu Road) (hereinafter referred to as the "S4 Highway Lifting Project") invested and constructed by Minhang District Urban Investment Company and constructed by Shanghai Road and Bridge of Tunnel Co., Ltd. will be ushered inThe west line Baotong Road was officially opened to traffic。This also indicates that the first phase of the project is basically over, and the second phase of the main line elevated construction is about to begin.
Aerial photography of the starting point of the Baotong West Line (south side of Xinzhuang Interchange).
Aerial photography of the end point of the Baotong West Line (south side of the Jindu Road Bridge).
It is reported that the main line elevated is planned to be opened to traffic in the second quarter of 2025, and after the raised high-speed is put into use, the construction of the third phase of the ground auxiliary road will begin in the second quarter of 2025, and the ground auxiliary road is planned to be opened to traffic by the end of 2025.
Renderings of Yindu Road nodes
The passage is partially preserved
Baotong Passage starts from the south abutment of Xinzhuang Interchange in the north, and reaches the abutment on the south side of the Jindu Road Crossing Bridge in the south, which is arranged on both sides of the current S4 Expressway, of which the west line is about 362 km, the eastern line is about 359 km.
The opening to traffic this time is the West Line Baotong Road. The reporter saw at the scene on the 27th that the on-site construction personnel were in full swing to carry out the construction of asphalt pavement and auxiliary facilities such as mechanical and electrical monitoring, street lights, and anti-collision guardrails.
Specifically, starting in the early morning of the 29th, the original high-speed passing vehiclesOn the south side of the Xinzhuang interchange, the vehicle will drive west to the newly built Baodao Road, and on the south side of the Jindu Road cross-line bridge, the vehicle will drive east to the original highwayThe Xinzhu Road off-ramp, Chunshen Road off-ramp, Yindu Road off-ramp and Jindu Road off-ramp along the line remain unchanged, and the whole line of Baodao Road maintains two-way six-lane traffic, in order to ensure the safety of passing vehicles during the construction period, the design speed is 50 kilometers per hour.
Xue Yun, the person in charge of the project of Minhang District Urban Investment Company, introduced that in order to minimize the impact on the expressway and the surrounding road network during the construction process, before the construction of the S4 main line expressway, it is necessary to build new roads on both sides of the existing expressway to achieve "one and one".
Previously, the eastern line of Baodao Road had been opened at the end of November. "Judging from the eastern route Baotong Road, which has been completed and opened to traffic, the road surface is smoother than before, the congestion has been alleviated, and the driving noise for the surrounding residents has also been reduced. Shen Rongxiao, executive deputy manager of the S4 section of the lifting project of Shanghai Road and Bridge Co., Ltd., said that after the implementation of the Baodao Road, high-speed vehicles can be guided to transfer to the Baodao Road, and then dismantle or use the current main line to implement the main line elevated and roadAfter the implementation of the main line is completed, the high-speed vehicles will be transferred back to the main line, and part of the road will be transformed into a permanent ground auxiliary road.
There are 15 residential communities along the S4 section of the lifting project, involving 10 neighborhood committees. Due to the wide range of construction operations and the complexity of the surrounding conditions, it is very difficult to organize and implement the transportation organization. The project builder has organized the surrounding neighborhood committees, road and transportation authorities, and construction units to carry out special coordination for many times. Combined with the opinions of all parties and the actual situation, the plan was repeatedly adjusted and optimized to reduce the impact on public travel as much as possible, ensuring that the Baotong project was carried out in an orderly manner with "turning over and constructing".
After completion, the capacity of the lane will be doubled
In 2001, the construction of S4 Shanghai-Jin Expressway is one of the first batch of radioactive highways built in Shanghai, and it is also an important part of the Shanghai regional high-speed trunk highway "one ring, thirteen shots, one vertical and one horizontal, and multi-linked", starting from the S20 Shanghai Outer Ring Expressway Xinzhuang hub in the north, to Fengxian District and Jinshan District in the south, leading to Zhejiang Province, and is an important transportation corridor through Minhang District. In the early years, it was called Line 4, A4 Highway, and Xinfengjin Expressway.
However, due to the fact that it is built as a ground-level closed road, there are too many broken roads, resulting in poor east-west communication.
The current situation of S4 Hujin Expressway (Chunshen Road - Jindu Road) east-west road is only through Chunshen Road and Jindu Road, and Yindu Road and Meizhou Road are cut off by S4 Expressway. Yindu Road is cut off as the main arterial road of the cross-river, and the east-west traffic needs to be detoured about 5 kilometers north via Chunshen Road or about 3 kilometers south via Jindu Road8 km.
Comparison of the current east-west Yindu Road bypass and the completion of the project
These blocked east-west surface roads have become a "heart disease" for citizens to travel.
The implementation of the S4 highway lifting project is imminent. The scope of implementation of the project is:Xinzhuang Interchange to Jindu RoadAfter the main line of expressway will be transferred from Xinzhuang Interchange, it will be lifted across Xinzhu Road, Chunshen Road, Chunshentang, Yindu Road, Meizhou Road and Jindu Road, and connect to the current ground section of S4 Highway south of Jindu Road, with a total length of 36 km.
It is by no means easy to upgrade the "main artery" of this city that has been "in service" for more than 20 years.
Schematic diagram of the project location
How to build a road?Wang Hao, the technical director of the lifting project of Shanghai Road and Bridge S4 into the city of STEC, made a vivid statement, and lifted this section of the highway at high speed, which was doneThree-dimensionalThe upgrade, from the north-south direction, is divided into two layers of upper and lower traffic, with two-way six-lane high-speed above and six-lane two-way ground road belowThe north-south road network has doubled the capacity of lanesAt the same time, it has the function of non-slow walking;From the east-west point of view, after the completion of the implementation of the project, the east-west traffic of Yindu Road and Meizhou Road will be directly opened, and the straight distance between the two intersections is only 70 meters, and it can be used to a large extentAlleviate the traffic congestion on Chunshen Road and Jindu Road
To create a new highland of innovation, opening up and development, and promote modernization and high-quality development, urban transportation renewal is the primary condition and necessary prerequisite. After the completion of the S4 highway lifting project, it will eliminate the east-west space separation in the surrounding areas of Xinzhuang and Zhuanqiao, improve the regional road network, reduce the burden of the north-south trunk line, and at the same time, the landscape greening along the line will also be upgraded and transformed, greatly improving the travel experience and living experience of surrounding residents, helping to realize the development strategy of "one south and one north" in Minhang District, supporting the construction of the sub-center of the main city of Xinzhuang, optimizing the hard power of business, and providing favorable conditions for regional integrated development.
Overall construction deployment
The project is implemented in three phases:
Phase 1:New roads will be built on both sides of the existing expressway.
Phase 2:After the implementation of the Baodao Road is completed, the high-speed vehicles will be transferred to the Baodao Road, and the existing main line will be removed or used to implement the main line elevated and road.
Stage 3:After the implementation of the main line is completed, the high-speed vehicles will be transferred back to the main line, and the Baotong Road will be transformed into a permanent ground auxiliary road.
Progress of the project
September 16, 2022After completing the first phase of traffic diversion and reform work for the nodes of Xinzhu Road, Chunshen Road and Yindu Road, a total of 6 groups of upper and lower Baotong ramps on the Baotong East-West Line have been completed.
July 9, 2023Completed the Chunshen Road node 35 of the Baotong East LineThe 4-meter main span steel temporary bridge was erected.
July 22, 2023Completed the Jindu Road node 35 of the Baotong East LineThe 25-meter main span steel temporary bridge was erected to realize the overall structural breakthrough of the Baotong East Line.
September 26, 2023Completed the first overall turnover task of the Baotong East Line.
November 18, 2023The three lanes of the Baotong East Line were completed, and the Baotong East Line was fully put into operation.
November 20, 2023Completed the Jindu Road node 36 of the Baotong West LineThe 2-meter main span steel temporary bridge was erected.
December 8, 2023Completed the Chunshen Road node 39 of the Baotong West Line1-meter main-span steel temporary bridge erection.