Recently, the reporter visited the 7 bid section of Yangxin Expressway and learned that the current construction of the bid section is in full swing, and the overall construction is progressing smoothly, of which the pile foundation of the Tanshui River 2 extra-large bridge has been completedThe erection of the beams is expected to begin at the end of this month.
Tanshui River 2 extra-large bridge.
It is located in Shuangjiao Town, Yangchun City.
Connecting the Shuangjiao Tunnel and the Shuangjiao Interchange.
At present, the construction of the bridge is proceeding in an orderly manner.
It can be seen at the construction site.
Workers are busy.
Rebar binding and welding.
Intensify the construction of piers and tie beams.
Wang Chengzhu, project manager of Yangxin Expressway Civil Engineering 7 of China Railway Fourth Bureau:
The Tanshui River 2 bridge has a total length of 1,365 meters and a total of 45 spans, which is the longest bridge in this section and the first bridge with girders. At present, the pile foundation has been completed, the pier stud and cap beam have been completed more than 80, and the beam is expected to be erected by the end of this month, and all erections will be completed in March 2024.
Yangxin Expressway Civil Engineering Section 7 was constructed by China Railway Fourth Bureau.
The length of the whole line is 12058 km.
Among them, there are 16 sections of roadbed and 1 tunnel5 seats.
There are 14 bridges and 1,773 precast beams.
The civil works are scheduled to be completed by the end of 2024
Since entering the site, the bid section has successively solved the problems of difficult approval of red line land, large amount of land acquisition and demolition tasks, complex relocation and transformation of three power plants, and difficult construction organization and coordination, and is the first unit to complete the requisition and demolition work on the whole line, and completed the important node project of the first double-line tunnel breakthrough in the Yangjiang section.
At present, the bid is actively organizing construction and production in accordance with the owner's annual construction and production plan, and it is expected that the owner's annual construction and production plan target will be reached by the end of this month.
Wang Chengzhu, project manager of Yangxin Expressway Civil Engineering 7 of China Railway Fourth Bureau:
Combined with the city's 100-day action, our department made full use of the construction period to make full use of resources and pay close attention to the progress. At present, there are more than 1,000 management personnel and labor personnel in our department, more than 100 sets of equipment, and a monthly output value of nearly 100 million yuan. At the same time, we should pay close attention to safe production, strengthen education and training and hidden danger investigation and management, and implement the safety production responsibility system for all employees, so that everyone stresses safety and will respond to emergencies to ensure the safety of construction and production.
Yangxin Expressway is jointly invested and constructed by China Railway and China Railway South, and is a component of the "seven horizontal" in the main skeleton layout of "12 vertical, 8 horizontal, 2 rings and 16 shots" of the expressway network in Guangdong Province, with a total length of 14191 km.
Entering the fourth quarter, the participating units of the project will continue to pay close attention to safe production, accelerate the construction progress, and complete the construction period goals as soon as possible.