On December 21, it was learned that the heating facilities of Jimo Land Port Airport Yunchuang Center were planned to be built, with a total investment of 36180,000 yuan, built by Ganghua Tongrui (Jimo) Energy Development.
No. 222, Zhanqian Street, Lancun Street, Jimo District, Lugang Linkong Yunchuang Center is a key pre-project in Shandong Province and Qingdao City, planning to take the industrial park as the carrier, with industrial buildings, industrial plants, and R&D office buildings as the main development objects, integrating investment, development, management and service, and focusing on the construction of an industrial complex of productive services such as headquarters office, R&D, and training.
The construction area of the second phase of the project is 39,331m, including office space, staff dormitory and supporting service rooms.
The boiler room of the project is located in the garage on the north side of the 5th floor of the first phase of the Lugang Linkong Yunchuang Center, covering an area of 230m and a construction area of 230m. The southeast side of the boiler room of the project is the control room and duty room, the east side is equipped with 4 boilers, the west side is the water pump and other equipment, and a 43m chimney is set up from the side of the sewage treatment plant in Lancun Town, northwest of the boiler room, which leads directly to the roof of the 5th floor. The pipes are arranged along the perimeter of the boiler, and the plane layout is reasonable. Construction of 2 sets of 035MW high-efficiency low-nitrogen condensing gas hot water boiler (mutual backup) and 2 sets of 14MW high-efficiency low-nitrogen condensing gas hot water boiler (mutual backup), annual operation time 141 days, 24h a day.