At the beginning of the Year of the Dragon, spring returned to the earth, and on February 17, at the construction site of the double-line lock in Linhuaigang, Huoqiu County, builders from all over the country bid farewell to their families and returned to work in advance, and devoted themselves to the construction of the Huaihe River waterway with vigor and enthusiasm, showing their responsibility for the early realization of the beautiful vision of the 2,000-ton ship traveling the Huaihe River waterway.
The Linhuaigang double-line lock project is located in the middle reaches of the main stream of the Huaihe River, Huoqiu County, Linhuaigang hub, the construction standard is a grade lock, which can be navigated by a single line of 2,000-ton ships, and the one-way annual freight volume is expected to reach 21.18 million tons. The project officially started in June 2021, and it is planned to be completed and opened for trial navigation in June 2024, which will greatly improve the navigation capacity of the Huaihe River channel and meet the navigation needs of large ships. The double-line lock will also be through the "diversion of the Yangtze River to the Huaihuai" water transport project, from the Huai River along the Yangtze River to the Shanghai Port, sailing to five continents and seven oceans, to the sea map strong, will greatly promote Lu'an City, Huoqiu County to achieve the development strategy of "hand in hand with Hefei, the Yangtze River Delta on the chain, and embrace Shanghai", so that local iron ore, wood products and other characteristic commodities through the Huai River route to the sea and to the world.
Gate chamber operation site).
Yin Jiawei, the person in charge of the project site, introduced that when the Spring Festival of the Year of the Dragon arrived, the project construction department planned in advance, organized personnel to clarify their responsibilities, and did a good job in continuing the connection work, so as to ensure that the work of engineering construction during the holiday period can be connected smoothly and smoothly after the holiday, and there will be no connection breakpoints or chaos of starting over. Arrange personnel to be on duty during the holiday and prepare for resumption of work after the holiday, and at the same time do a good job in the mobilization of personnel returning to their hometowns and transportation guarantees, so as to ensure that personnel can return to work on time and on schedule, and speed up the construction progress of the double-line lock with higher enthusiasm, faster speed and higher standards, so as to ensure that the planning map will be turned into a real picture as soon as possible, so that all types of ships in the Huaihe River waterway can sail unhindered, and contribute to the development of the regional economy to the river and the sea and to the world.
At present, the construction unit is stepping up the safety inspection before resumption of work in the gate construction, decoration, curtain wall and other operation areas to ensure that safety measures are in place. At the same time, safety education will be carried out for returning workers, and special safety training will be carried out before resumption of work to ensure that the builders enter their respective jobs with a high-spirited attitude of being alive and vigorous, and promote the pre-navigation of the Linhuaigang double-track lock as soon as possible. (Huoqiu County Transportation Bureau Road Army).
*: Lu'an Municipal Transportation Bureau.