Hello everyone, I'm Brother Xue. Recently, the readers of the VIP member group consulted the installation and construction plan of the rail robot, and today shared a detailed implementation plan for the automatic inspection of the robot in the smart distribution room, which is very detailed, and it is recommended to collect it for later use.
This complete set of word materials, VIP members can directly send me a private message if they have needs,**
Construction and installation plan
1.Workflow
Figure 6-1 Installation workflow
2.Construction organization design
The installation of a track camera system (9 meters track, including mounting equipment) requires 2-3 people (2 people to hoist the track), the installation work takes one day, and the commissioning and acceptance take half a day.
3.Construction organization chart
Figure 6-2 Construction organization diagram
The system needs to arrange mature technology, experienced construction and installation personnel for installation, set up an installation team leader, command and coordinate on-site installation and supervise the safety management in the installation process, arrange 3-4 constructors to carry out on-site installation work, because the on-site installation involves electricity, ascending (below 4 meters) and long equipment installation and other special processes, the safety awareness of the constructor, the technical level is a little higher requirements, so the construction organization design is very important, and the construction should be carried out in strict accordance with the safety specifications of electric power operations.
4.Construction schedule drawing
Figure 6-3 Construction schedule.
5.Installation instructions
Description of T-type hoisting connectors
1) T-type ceiling connector and T-type hoisting connector.
larger) (smaller).
2) Height-adjustable connecting rod and hoisting connecting rod.
Height-adjustable connecting rods and hoisting connecting rods can be spliced, elongated and shortened.
Rail installation – installation of hoisting brackets
The installation of the track is to fix the vertical hoisting bracket in the mounting groove of the track with screws and side screws through the L-shaped connecting plate (installed on both sides of the upper edge of the track).
hoisting bracket) (L-shaped connecting plate).
1.Top screw 2Side screws 3Mounting groove hoisting installation effect.
Rail-to-track connections
Track-to-track connections:
The L-shaped connecting plate configured directly with the hoisting bracket above is screwed into the mounting groove at the upper edge of the track. (as shown below).
The upper end of the inter-track connection (L-shaped connecting plate) The effect of the upper end of the inter-track connection.
The lower part is screwed into the mounting groove on the lower edge of the track with the standard rail connector, one every 3 meters. (as shown below).
The lower end of the track is connected to the overall installation effect of the connection between the tracks.
Installation of the rack
The rack is mounted on the other side with the notch of the e-chain® and is screwed in the mounting groove of the rail. (as shown below).
Rack mounting effect.
3.5.Install the photoelectric limit switch (install as shown).
Note: The eyes of the photoelectric limit switch should be parallel to the rail machine as shown in Figure 1
Install the rack and pinion
When installing the rack and pinion, the shell of the orbital robot needs to be removed first, revealing the gears.
Loosen the gear screw 1, adjust the up and down position of the gear until the connection between the gear and the rack is just right, can not be too tight or too loose, and then tighten the screw 1 after adjustment, and fix the position of the gear.
Introduction to the latest boutique information
This set of weak current data summarizes a large number of technical documents, 313 PPT schemes, 279 standard specifications, 60 design schemes, 119 drawing materials, 8 sets of construction drawings, 20 sets of bills of quantities, 20 construction organization designs, 69 visio topology diagrams and blocks, 54 excel**, complete construction process documents and acceptance documents, etc., which are very comprehensive.