Feasibility study report of 500 tons of sewage treatment center construction project

Mondo Finance Updated on 2024-02-01

1. Basic information of the project

The project uses the vacant land in the company's west plant area to build a new sewage treatment center, and at the same time purchases complete sets of sewage treatment equipment such as wastewater lifting pumps, storage tanks, mixers, separators, etc., and forms a daily sewage treatment capacity of 1,500 tons after the completion of the project. The total investment of this project is 5,100000,000 yuan. The main body of implementation is Zhejiang Zhongxin Fluorine Co., Ltd., and the implementation site is located in the existing factory area of Shangyu Economic and Technological Development Zone, Hangzhou Bay.

2. The necessity of the project

There are 2 sewage treatment stations in the company's west plant area to treat the wastewater of the existing project, with a sewage treatment capacity of 600 tons per day. The existing 2 sewage treatment stations were built earlier and have been in operation for a longer time. With the continuous development of the company and the increase of product types, it is expected that the treatment scale of the existing sewage treatment station in the plant area will be difficult to meet the needs of the company's development after the planned project is put into operation. Therefore, considering the company's long-term development, it is proposed to build a new sewage treatment station with a designed treatment capacity of 1,500 tons per day.

3. Project feasibility

The company's existing sewage treatment station has been in operation so far, and the sewage treatment facilities are operating normally and stably, and the effluent quality is qualified. After years of development, the company has accumulated rich experience in sewage treatment operation and maintenance, which can meet the needs of the construction and operation of the project and provide a full guarantee for the construction and operation of the project.

4. Project construction cycle

The project is expected to have a construction period of 24 months.

5. Project investment estimate

The total investment of this project is 5,100000000 yuan, of which the construction investment is 5,00000000000000000000000000000000000000000000000000,000 yuan.

6. Approval of the project

The land for this project is self-use. The project has obtained the "Zhejiang Province Enterprise Investment Project Filing (Coding) Information Form" issued by the Management Committee of Hangzhou Bay Shangyu Economic and Technological Development Zone, Shangyu District, Shaoxing City, project code: 2111-330604-99-02-666735. The project has been approved by the EIA.