"Annoying, there is a big traffic jam on the highway every year during the Spring Festival, and I really hope to take the high-speed rail back and forth, but the high-speed rail ticket is too difficult to grab. "Mr. Wang is a native of Meizhou, a person who works hard in Guangzhou, and has already bought a private car, but he doesn't want to drive back to his hometown every New Year's holiday, because the road to and from Meizhou is too congested, and it takes at least 8 hours or even 15 hours to drive a trip, which is really too tiring, and I believe that there are not a few Meizhou people who have the same idea as Mr. Wang.
Mr. Longwang took the high-speed rail home on the return of the Spring Festival, and the wish that it was no longer difficult to grab tickets was being realizedAccording to the Guangzhou Railway Bureau, the operator of the Meilong high-speed railway, during the Spring Festival holiday, more than 1,200 builders from all over the country worked day and night on the construction site of Meilong, and they will ensure that the construction of the ballastless track bed of the Meilong high-speed railway is completed as planned, providing the foundation for the subsequent track laying of the whole line, and ensuring that the Meilong high-speed railway has the conditions for opening in 2024.
Meilong high-speed rail is the solution to alleviate the difficulty of grabbing tickets mentioned by Mr. Wang, Meilong high-speed rail starts from Meizhou West Station of Meishan high-speed rail in the east, and runs through two groups of contact lines to the west through the direction of Shenzhen and Ganzhou of Ganzhou-Shenzhen high-speed railway, and the design speed of the line is the same as that of Ganzhou-Shenzhen high-speed railway, and the new Xingning South Station and Wuhua Station two intermediate stations, Meilong high-speed rail will realize Meizhou City, Xingning City, and Wuhua County into the ranks of 350km h high-speed rail coverage. The geographical location and operation path of the Meilong high-speed railway are as follows:
Schematic diagram of the geographical location and running path of Meilong high-speed rail From the above figure, Guangzhou to Meizhou will pass through Guangzhou-Shenzhen Railway + Guangzhou-Shantou High-speed Railway + Ganzhou-Shenzhen High-speed Railway + Meilong High-speed Railway, Shenzhen to Meizhou will pass through (Guangzhou-Shenzhen Railway) + Ganzhou-Shenzhen High-speed Railway + Meilong High-speed Railway, Guangzhou-Shenzhen area to and from Meizhou train running path can no longer bypass Xiamen-Shenzhen Railway + Meishan High-speed Railway, trains no longer need to run in Chaoshan Station in the opposite direction, so that more shifts can be opened, more tickets are provided, after the opening of Meilong High-speed Railway, The likelihood that Mr. Wang will be able to buy a bullet train ticket has greatly increased.
So can the Meron high-speed rail be opened within the year? Let's help Mr. Wang analyze and analyze, first take a look at other project progress nodes, such as the Shanshan high-speed railway, which just opened last year
Shanwei to Shantou South Section of Shantou High-speed RailwayTrack laying will begin on June 6, 2023Track laying will be completed on July 22, 2023On October 16, 2023, the joint commissioning and joint test will beginIt will be put into operation on December 26, 2023, from the beginning of track laying to the opening,It lasted 203 days, almost 7 months.
Mr. Wang can pay attention to the progress of the Weston high-speed rail according to the above time nodesAssuming that the Meilong high-speed railway will be opened on June 30, 2024, then the track laying of the whole line will have to start in December 2023, but the construction of the ballastless track bed is still underway, so it is obvious that it is difficult for the Meilong high-speed railway to meet the opening conditions on June 30, 2024.
Or assuming that the Meilong high-speed rail will be opened on December 26, 2024, it is more reliable, according to the progress of the Shanwei to Shantou southern section of the Shantou high-speed railway, then the whole line of the Meilong high-speed rail will start laying tracks on June 6, 2024 at the latest, according to the Guangzhou Railway Bureau, at present, the tunnels, bridges, and roadbed projects of the Meilong high-speed rail project have all been completed, and the track project is being pushed forward quickly, and it is believed that the track laying will start before June 6, 2024. In addition, the construction of the four power plants and station buildings is also being accelerated.
The bridges, tunnels and roadbed works of the Meilong high-speed rail project have all been completedLet's look forward to the opening of the Meilong high-speed rail on December 26, 2024.