Please check! The latest progress of key projects in Fengxian New Town

Mondo Social Updated on 2024-02-07

The Spring Festival of the Year of the Dragon is approaching.

Looking back on the past year.

The builders of Fengxian New City have worked hard and sweated.

Contribute to the construction of the city.

Next, take stock together.

The latest progress of key projects in Fengxian New Town.

On the water side

The land area on the water side is 16,755 square meters, the total construction area is 29,704 square meters, 19,021 square meters above ground, and 10,684 square meters underground.

At present, the main structure of the project has been completed, and it is in the construction stage of the second structure, and it will enter the stage of mechanical and electrical installation and curtain wall construction after the year, and it is planned to be completed in the second half of 2024.

Nine Trees Hotel

Nine Trees Hotel has a land area of 49,589 square meters, a total construction area of 68,565 square meters, 38,888 square meters above ground and 29,677 square meters underground. In the environment of the Nine Trees Future Art Center and the forest landscape, through the cracks that resemble canyons between the green hills, the Nine Trees Hotel can vaguely see the unique Jiangnan Water Street space inside.

At present, the project has completed the construction of the substructure and is in the stage of superstructure construction.

World Foreign Language School

With a land area of 57,797 square meters and a total construction area of 54,400 square meters, the school is a kindergarten with 15 classes, a primary school with 20 classes and a middle school with 16 classes.

At present, the project has completed the construction of the superstructure, and is in the stage of mechanical and electrical installation, indoor and outdoor decoration and outdoor overall construction, and is scheduled to open in September 2024.

Zhiyuan High School

Zhiyuan High School, with a total land area of 46,592 square meters and a total construction area of 61,285 square meters, is a 36-class boarding high school.

At present, all the units of the project have been structurally completed, and are in the stage of indoor and outdoor decoration construction and outdoor overall construction, and it is planned to open in September 2024.