Due to the recent period of time to consult 4mm lead plate installation technology process related to the problem of more people, here is a recommendation to you related to this article, if you are interested, you can read it and collect it.
4mm lead plate installation technology process
1. Preparation: check the working area, ensure that the foundation wall is flat, clean up the debris and dust on the wall, and determine the installation layout.
2.Lead Plate Measurement & Cutting: Use a tape measure and ruler to measure and cut a 4mm lead plate according to the wall size and design requirements.
3.Arrange the installation line: According to the design requirements and the size of the wall, use ink lines or other tools to mark the installation line on the wall to ensure the position and flatness of the lead plate.
4.Nailing: Use lead plate nails or screws to install the lead plate on the wall, making sure that each lead plate is firmly fixed to the wall. The spacing of the nails or screws should be in accordance with the relevant code requirements.
5.Check and adjust: During the installation process, it is necessary to regularly check the verticality and flatness of the lead plate, and if it is found that it does not meet the requirements, it needs to be adjusted or corrected.
6.Caulking: After installation, use sealant or other materials to fill the gaps between the lead plates to ensure no water leakage and sealing effect.
7.Cleaning and sorting: clean up the garbage and sundries generated during the construction process, tidy up the installation area, and keep the installation environment clean and tidy.
8.Acceptance confirmation: After the installation is completed through the above steps, the final acceptance is carried out to ensure that the installation quality meets the specifications and requirements.
Installation Specifications & Requirements:
1. The installation of lead plates should meet the requirements of relevant architectural design and engineering specifications.
2.The installation location, size and layout of the lead plate should meet the design requirements and the predetermined construction plan.
3.The installation spacing, use of fixtures and installation methods of lead plates should comply with relevant specifications to ensure safety and firmness.
4.When using fixings, it is necessary to pay attention to the distance and number of fixings from the edge to meet the requirements of relevant specifications to ensure the fixing effect and stability.
5.The installation of the lead plate should maintain the verticality and flatness, and if there is any deviation, it needs to be adjusted and corrected in time.
6.After the installation of the lead plate is completed, the gap should be filled and sealed to ensure that there is no water leakage and sealing effect.
7.Protective measures should be taken in the construction area during the installation process to ensure the safety and cleanliness of the construction environment.
8.The installation acceptance should be comprehensively inspected to ensure that the installation quality meets the specifications and requirements.