On January 20 this year, the Dongfeng Dam remediation and restoration project located in the Caohai area passed the preliminary acceptance and was open to the public free of charge. This scenic waterfront spot attracts a large number of tourists during the Spring Festival.
In addition, the supporting facilities of the Dianchi Lake Greenway are also being improved, including 12 public toilets in the section around the Caohai Sea, which are expected to be completed by the end of the first quarter of this year.
The open Dongfeng Dam attracts a large number of tourists to check in.
Dongfeng Dam is located in the north area of Caohai in Kunming, north of the Yunnan Greenway next to the Xinyunliang River, and west of the Gaoyao Interchange Wangjiadui Wetland.
The construction will be coordinated by the Kunming Municipal Bureau of Housing and Urban-Rural Development.
According to the relevant person in charge of Yunnan Zhenghao Construction Engineering Company, the construction unit of the project, the remediation and restoration project entered the construction site on February 1 last year, and according to the actual situation of the project, it was divided into four construction sections: the southern section, the middle section, the pontoon section and the northern section, which was basically completed in early January this year.
Dongfeng Dam landscape.
The total length of the road is 3,450 meters, and the width of the trail is 2 meters to 4 meters.
Among them, the southern section is 1,450 meters wide and 4 meters wide, retaining the original tall eucalyptus trees and aquatic vegetation, forming a beautiful boulevard.
The middle section is 1500 meters long and 2 meters wide5 meters, the east side is a hard revetment, and the west side is a green plant revetment, which plays the original role of the reeds that are full of embankments, and supplements some hydrophilic trees and ground cover such as metasequoia and Yunnan willow to form a natural ecological sightseeing greenway.
The northern section is 360 meters long and 2 meters wide, which is an ecological corridor connecting the seven-hole pontoon bridge and the greenway around Yunnan, with a new lighting and monitoring system, and convenient facilities such as rain shelters, landscape stones, gabion benches and wooden stakes benches set up along the line, which enhance the landscape effect and facilitate the leisure and sightseeing of tourists.
The "landmark" of Dongfeng Dam, the seven-hole pontoon bridge, is 130 meters long, and the façade is made of grid mesh aluminum square pass, which retains the beauty of the classical bridge and effectively reduces the wind load of the pontoon bridge on the water surface.
Dongfeng Dam has become a good place for citizens to enjoy water and leisure.
After the completion of the construction of the Dongfeng Dam, shuttle between the green water in the center of the Dianchi Caohai Lake, passing through the green embankment, the reed embankment, the seven-hole pontoon bridge and the grass embankment, visitors can immerse themselves in the scene, taste the beauty of "the beauty of the west, the reed land of the apple, the green feather Danxia, the spring willow", and enjoy the natural scenery of "the clear water and green mountains reflect the Danxia, and the willow bank reed embankment welcomes the green feather".
Stand on the Dongfeng Dam and enjoy the scenery of the mountains and rivers.
At present, the open Dongfeng Dam attracts a large number of citizens and foreign tourists to check in every day, watch the sunrise in the morning, watch the blue sky and white clouds during the day, overlook the West Mountain, see the sparkling Dianchi Lake, wait for a romantic sunset in the evening, every frame is a beautiful landscape painting. Many tourists have shared beautiful photos and ** on online platforms such as Douyin and Xiaohongshu.
All 12 public toilets in the Huancaohai section are expected to be completed by the end of the first quarter.
The planned total length of the Dianchi Greenway is 137 kilometers, of which the Dianchi Greenway from the Huancaohai section and the Haigeng Park to the three peninsulas is about 37 kilometers long1 km, which was basically completed on April 30, 2022. The Dongfeng Dam opened this time is closely connected to the Huancao Sea section.
With the 23-kilometer section of the Dianchi Lake Greenway around the Caohai Sea becoming an important place for citizens to sightsee, relax and fitness, Kunming Dianchi National Tourism Resort is also actively accelerating the construction of supporting facilities.
On January 1, 2024, six public toilets were put into use in the Huancaohai section of the Dianchi Greenway, and eight public toilets have been put into use in addition to the two that opened last year. The four public toilets under construction are also progressing rapidly, and it is planned that all of them will be completed by the end of the first quarter.
In the future, when citizens visit the section of the Dianchi Greenway around the grass sea, they will no longer have to worry about the problem of "convenience".
According to Kunming's "Planning Guidelines for Public Toilets along the Dianchi Greenway - Huancaohai and Haigeng Park to the Three Peninsulas", it is planned to build 15 new public toilets along the section of the Dianchi Greenway from Caohai to the Three Peninsulas. Among them, there are 12 in the Huancaohai section.
Location map of public toilets (**Kunming planning and construction).
The plan shows that the design of the public toilet highlights the design concept of "one toilet and one case", and each public toilet will become a unique landscape, harmoniously integrated with the surrounding environment, and has its own characteristics, which can better integrate into the surrounding environment of the Dianchi Greenway on the basis of meeting the basic functions of the public toilet, and improve the quality of the landscape along the line.
The interior of the public toilet will pay attention to the improvement and humanization of the facilities to ensure that the facilities are complete and functional.
The following are some renderings of public toilets.
Eight public toilets have been put into use, namely:
China Railway Park Public Toilet, which was put into use on October 1, 2022;
The public toilet of the Gemdale project will be put into use on October 20, 2023;
Public toilet in the first auto repair factory.
Public toilet at the intersection of Zhizhen Road.
Public toilet at No. 2, Section 4, Huanhu Road.
Xiba Hebei public toilet (public toilet part).
Public toilet at the west exit of Caohai Tunnel.
Public toilet on Haiyuan South Road (public toilet part).
3-8 will be officially opened for use on January 1, 2024.
There are 4 public toilets under construction, namely: Wangjiadui Wetland Public Toilet, No. 1 Wetland Public Toilet, Lehaicheshi Public Toilet, and Wulonghe Public Toilet. It is scheduled to be completed and put into use by the end of the first quarter of 2024.