Cement photovoltaic piers are an indispensable part of the photovoltaic system, mainly used to support and fix photovoltaic panels. Its rugged nature allows the PV system to operate reliably in a wide range of environmental conditions. Below, we will introduce the use of cement photovoltaic piers in detail.

1. Preparation before the installation of cement photovoltaic piers.

Before installing cement photovoltaic piers, it is necessary to make adequate preparations. First of all, it is necessary to ensure the safety of the construction site and avoid construction in bad weather or unfavorable environments. Secondly, check whether the specifications and quantity of cement photovoltaic piers meet the design requirements and confirm that their quality is correct. At the same time, prepare the required tools and materials, such as hammers, wrenches, levels, expansion bolts, etc.

Second, the installation steps of cement photovoltaic piers.

1.Determine the installation location: According to the design requirements of the photovoltaic system, determine the installation position of the cement photovoltaic pier. Use a level to ensure that the ground is level to ensure that the photovoltaic panels are installed at the correct angle.

2.Excavation of foundation pit: according to the size and depth requirements of cement photovoltaic piers, excavate suitable foundation pits. The bottom of the foundation pit should be flat to ensure that the cement photovoltaic pier can be placed stably.

3.Place the cement photovoltaic pier: Put the cement photovoltaic pier into the foundation pit and adjust its levelness with a level. Ensure that the cement photovoltaic pier is in close contact with the ground and there is no shaking.

4.Fixing cement photovoltaic piers: Use expansion bolts or other fixing parts to fix cement photovoltaic piers in the foundation pit. Make sure that the fixation is firm and not easy to loosen.

5.Check the installation quality: After the installation is completed, check the horizontality and verticality of the cement photovoltaic pier to ensure that it meets the design requirements. At the same time, check whether the fixing parts are firm and reliable.

3. Maintenance and use of cement photovoltaic piers.

After the installation of cement photovoltaic piers is completed, regular maintenance and inspection are required. Regularly check whether the fixing parts are loose, and if they are loose, they should be tightened in time. At the same time, check whether there are cracks or damage to the cement photovoltaic pier, and repair or replace it in time if there is. During use, avoid hitting or stepping on the cement photovoltaic pier to avoid damage.

In conclusion, the use of cement photovoltaic piers is relatively simple, but attention to detail and safety are required during installation. Proper installation and maintenance can ensure the stable operation of the photovoltaic system and improve the efficiency and service life of the power generation. If you need a PV pier, contact me through the homepage.