Engineering cost software application Civil engineering three dimensional takeoff software applicati

Mondo Technology Updated on 2024-01-31

Stratigraphic merger.

For the excavated pile, because some quotas require that the hole pile with soil and stone is calculated separately according to the different depths of the soil layer and the rock, the calculation object of the formation calculation is no longer the specific component attribute of the hole pile, but becomes the stratum category one level lower than the component attribute;The calculation carrier is no longer the component arranged in the engineering model, but becomes the formation set on the hole pile component, which is reflected as the depth of one of the distinguishing conditions of the formation excavation engineering quantity, and the depth of the formation should not only be taken from the hole depth attribute of the component, but the formation depth should be selected according to the specific requirements. In order to take into account the needs of hole pile calculation in different regions, the software designs a special processing method for the hole engineering quantity from definition, setting, analysis, statistics to output, including the following contents:

1) The method of determining the depth of the excavated pile is controlled by parameter rules. As shown in the figure, the "pile foundation" component below the calculation rule parameter rule is provided with the [method for determining the depth of the excavated pile] parameter rule on the takeoff setting calculation rule, except for method 1 and method 2 for individual areas, most of the applicable method 3 does not consider the depth of the formation, that is, the hole depth attribute of the component is taken from the component when the depth condition is specified in the quota.

2) Set the conditions for distinguishing the engineering quantity of the stratum by the earthwork definition of the engineering characteristics. As shown in Figure 4-17, there is "Ground Quantity Discrimination Condition" under the Engineering Characteristics Definition of Engineering Settings. From the dialog box that opens, you can see the criteria for distinguishing the formation quantities, in addition to the depth, there are also "diameter" (which should be understood as the aperture or side length) and "dry and wet soil". Click the Help button at the bottom of the dialog box to see the description of the settings for distinguishing conditions.

3) What you see is what you get in the component check interface. As shown in the figure, after the excavated pile is processed by the original parameter method and changed to the graphic method, what the user sees when checking the engineering quantity means what the software calculates.

4) the quantity output is not provided with the amount of ground excavation quantity project, as shown in the figure, the amount of formation excavation project of the excavated pile is no longer like other output items of the hole pile, set in the quantity of calculation setting quantity output page. Therefore, the user's habit of hooking the hole quantity from the number or component needs to be changed, and the hooking practice can only be done after the result of the statistical preview interface or the physical quantity result is obtained.

Volumizing treatment. The filling problem of the amount of excavated pile pouring engineering can be summarized into two categories:

1) According to the design pile (or wall) section expansion of a certain size, the volume of the increase in filling is reflected in the engineering quantity. In this regard, the software provides two parameter rules of [calculation method of excavated pile wall protection] [calculation method of pile core in section without wall protection section of excavated pile] on the "pile foundation" component under the calculation rule parameter rule of takeoff setting, so as to carry out differential calculation, as shown in the figure. The previous hole pile parameter [filling expansion value] belongs to this category.

2) According to the calculation of the cross-section of the designed pile (or wall), the increase in the amount of pouring material caused by filling is reflected in the quota consumption. In this regard, the software divides the core volume of the pile core into the volume of the core with the wall and the volume of the core without the wall, so as to compensate for the expansion of the consumption through the quota conversion.

Foundation pit earthwork. Function description: Calculate large excavation earthwork.

Menu location: [Earthwork] [Foundation Pit Earthwork].

Command code: jktf

The definition of foundation pit is referred to the section on single foundation. The foundation pit layout selection bar is shown in the figure.

Importing Drawings Freezing Layers Manual Layout Point Internal Generation Rectangular Layout Pit Grading.

After executing the [Foundation Pit Earthwork] command, the command bar prompts:

Rectangular layout (exit) or manual arrangement (d) points are generated internally (j).

According to the prompt, you can draw the outline of the bottom surface of the foundation pit by hand or click in the closed polyline that represents the bottom surface of the foundation pit on the interface.

When the large foundation pit earthwork is excavated in multiple steps, if the slopes of each side of the plane and the upper and lower steps are different, the step heights of the upper and lower steps are not equal, or even the width of the walkway on each side of the plane and the upper and lower steps also changes, it can be edited with the [Foundation Pit Grading] command.

Options and Actions Explained:

Foundation pit grading] is used for the grading setting of the edge of the foundation pit to prevent the slope from collapsing.

Instructions: Execute the [Foundation Pit Grading] command, and the command bar prompts:

Select the modified large foundation pit:

According to the prompts on the command bar, select the large foundation pit that needs to be graded or change the step height and walkway width, and the "Modify Large Foundation Pit" dialog box will pop up after selection, as shown in the figure.

Dialog Options and Actions:

Current Modified Order] When there are multi-level walkways in the foundation pit, indicate the current modified step in " ", counting from the bottom to the top.

Excavation Depth] specifies the step height of the current tier.

Walkway Width] Specifies the width of the walkway on the current edge of the top face of the current step, and is grayed out when the specified step is the top step to indicate that it is not editable.

Grading Factor] Specifies the grading factor for the current edge of the current order.

After the pit grading function is executed, select the edge line that needs to be graded or modify the step height and walkway width on the large base drawing according to the prompts on the command bar. The edge line of the foundation pit has been arranged by the direction of the serial number in the system, and the selected edge serial number is displayed in the dialog box that is clicked. If you define the pit walkway order and walkway width when defining the pit number, you can see the corresponding data in the corresponding column in the dialog box. The default walkway order is 1, that is, there is no walkway in a single-stage large foundation pit, and the walkway order is not less than 2 large foundation pits, which can be edited and modified in the corresponding column.

In the dialog box, the three contents of [Excavation Depth], [Walkway Width] and [Grading Factor] can be modified as needed.

Apply All Edges] Clicking this button will match the parameters set in the dialog box to all edges of the pit.

Apply Current Edge] Click this button to modify only the selected edge order.

Cancel] Do nothing about the foundation pit and return to the original state.

Scope of construction. Function description: The building scope is mainly used for backfill deduction after the excavation of the large foundation pit in the basement. Because the basement is a space body, if the large foundation pit backfill earthwork follows the ordinary deduction of components, only the solid deduction of walls, beams, plates, columns and other components without deducting the space part, which is equivalent to filling the basement, and the result obtained is absurd. The scope of the building is to consider the area within the outer edge of the basement as a component to consider the deduction, so as to deal with the backfill calculation problem of large foundation pit with basement.

Menu Location: [Earthwork] [Building Range].

Command code: jzfw

The definition is the same as that described in the scaffolding.

The selection bar for the layout of the building scope is shown in the figure.

Import Sheets Freeze Layers Manually Lay Out Solid Periphery

Intelligent Arrangement Inside the Entity Line Selection Arrangement Rectangular Arrangement Adjust grips.

Options and Actions Explained:

Description of the same board.

Explanation of the [Component Placement Positioning Bar] on the corresponding navigator: None.

Corresponds to the [Attribute List Bar] on the navigator

Explanation: Same as scaffolding instructions.

Instructions: Instructions for the layout of the same board.

Layout of the venue. Function description: In the design of the general plan of the project or the large-scale land consolidation project, when the natural topography of the site is transformed, the area divided according to the different positions of each factor in the site layout (factory warehouse, freight yard, building, road, drainage, irrigation, etc.) on the ground elevation line is called the site area. The purpose of arranging the site is to automatically match the network design elevation of the grid earthwork by setting the site design elevation. Site layout is an auxiliary function for grid quantity calculation.

Cloth contours. Function description: For the site renovation project that expresses the natural terrain with contour lines, the natural elevation of the network of the grid earthwork is automatically collected by identifying (or hand-drawing) the contour lines. Cloth contours are also an aid to grid quantity takeoff calculations.

Grid earthwork. Function description: Grid layout for the design of the general project plan or large-area land consolidation project, which is used for the calculation of earthwork excavation and filling on large-scale sites.

Menu location: [Earthwork] [Grid Earthwork].

Tool icon: [illustration].

Command codename: wgbz

Instructions: After executing the command, the command bar prompts: select the polyline or field area that has been drawn, and the cursor changes to the "mouth" glyph, prompting the user to select the contour boundary boundary of the inserted electronic map or the grid earthwork manually drawn with the polyline in the interface.

Tips: To do mesh earthwork calculation, first use the multi-line line of CAD in the interface to draw the grid earthwork contour or field area that needs to be calculated, and it should be a closed contour or field area.

According to the command bar prompt, the cursor selects the polyline with a closed boundary in the interface, and then the command bar prompts:

Enter the grid side length x(m):<10>:, enter the grid spacing in the x direction in the command bar according to the prompts, such as enter "5" and press Enter, the command bar prompts:

Enter the grid edge length y(m):<5>:, enter the grid spacing in the y direction in the command bar, if the spacing in the y direction is the same as the x-direction, you can directly enter the grid. The command bar prompts again:

Select a point on the edge of the grid or inside as the starting point for the division: and click the cursor at the starting point of the grid line where you want to draw the line. The command bar prompts again: Please enter the square.

inclination or Parallel to the specified line (l)] <0>:

After entering the inclination angle, the system will use the clicked position as the origin point to arrange the grid lines in the direction of the inclination according to the set spacing, and generate the corner number and square number corresponding to each cell (Figure 4-24).

After the grid area is set, execute the [Earthwork] [Grid Earthwork] [Point Set Height] command, as shown in the figure.

After executing the [Set Point Height] command, the cursor will change to a cross shape, and the command bar prompts:

Specify the point at which you want to modify the natural elevation Specify the natural elevation (z) Specify the design elevation (s) and automatically collect the natural elevation (a).

After the cursor selects the point to modify the elevation, there is a red circle positioning displayed on the grid of the point we selected, and then a prompt will appear: enter the natural elevation (m): enter the natural elevation, and you can complete the elevation of the point.

You can also choose a different modified elevation method:

1) Natural collection: When choosing this method, you must first arrange the contour line, and the software will calculate the natural elevation of each point according to the contour line.

2) **Input: Box selection needs to be set high dots, the prompt of the point is: the first corner point, the cursor box the first point of the cell grid, drag the mouse, the set grid box selection, then the table input dialog box will pop up, as shown in the figure.

Enter the elevation value of each point, and click the [Confirm] button to complete the elevation of the point.

3) Specify Design Elevation: This is the interface that will switch to the design elevation setting interface for the site. Click the [Specify Design Elevation] button or enter s, press enter, and the command bar prompt will appear:

Specify the point at which you want to modify the design elevation Specify the natural elevation (z) Specify the design elevation (s) Automatically collect the natural elevation (a).

The operation reference for setting design elevations for a point is to set natural elevations. The natural elevation and elevation of a grid quantity are shown in the illication.

The data with the "—" sign in the figure is the cut. The red one is the fill area, and the blue one is the cut area.

Related Pages