Before installation, the installer must be familiar with the installation drawings of the fast door, check whether the line of the fast rolling door is in place, and make other installation preparations, including the parts and tools that need to be used.
Before installation, it is also necessary to check whether the size of the door is consistent with the size of the opening: whether the teaching quantity of the guide rail bracket is correct, whether the embedded parts of the opening are correct, whether the position of the embedded parts of the bracket is correct, etc.
Rapid rolling door installation process opening treatment: check whether the opening is consistent with the size of the product, the general width and height of the opening should not be greater than 5m, and review the position and quantity of embedded parts.
Spring line: Measure the elevation of the hole, and pop out the two guide rails vertically and the center line of the reel. Fixing the drum and transmission device: welding the backing plate on the embedded iron plate, fixing the left and right brackets of the drum with screws, installing the reel, the reel should rotate flexibly after installation, installing the reducer and transmission system, and installing the electrical control system.
No-load test: check whether the motor and reducer are working normally and whether the direction of rotation of the drum is correct after power-on. Curtain panel: Assemble the curtain board and install it on the reel.
Installation guide rail: according to the position specified in the drawing, the guide rails on both sides and above are welded firmly on the embedded parts of the wall, and welded into one, and each guide rail should be in the same vertical plane.
Commissioning: first manual test run, in the use of the motor to open and close several times, adjust to no stuck, blocking and abnormal noise and other phenomena, the speed of opening and closing to meet the requirements of all debugging, installation of protective equipment.
Cleaning: Painting or inlaying the decorative surface layer of the wall with rails and cleaning the site.