Bidding for the construction of the partial reconstruction project of the Lanxin Railway

Mondo Social Updated on 2024-01-31

On December 27, the "Bidding Announcement for the Total Construction Price Contracting of the JYGZG-SG Bid Section of the Jiayuguan Station Reconstruction Project of Lanxin Railway" was released. The project will officially start in April next year, with a planned construction period of 15 years. The estimated total amount of project investment is 64.8 billion yuan.

The Lanxin Railway is an important part of the road and bridge corridor, and it is also one of the main routes for the China-Europe train. Jiayuguan Station is the largest passenger and freight marshalling station in Hexi, Gansu Province, with the rapid growth of freight volume of the Lanxin Line, the utilization rate of Jiayuguan Station to the departure line has tended to be saturated, which has become a blocking point and pain point that restricts the large capacity of the Lanxin Trunk Line.

After the completion of this transformation, Jiayuguan Station is still used as a section station and a general speed passenger station, mainly handling technical operations such as the arrival and departure of ordinary speed passenger cars, the decompilation of freight cars, and the replacement of locomotivesThe Dacaotan direct field mainly handles the technical operations of trains without decompilation and replacement. It can greatly improve the overall freight capacity of the Lanxin Line and solve the problem of cross-interference between passengers and goods.

1. Bidding conditions

The reconstruction project of Jiayuguan Station of Lanxin Railway has been approved by China Railway Group with the "Reply to the Feasibility Study Report on the Reconstruction Project of Jiayuguan Station of Lanxin Railway" (Tie Fa Gai Han No. 2023 304) and "Approval of the Preliminary Design of Jiayuguan Station Reconstruction Project of Lanxin Railway" (Tie Jianhan No. 2023 442), and the project owner is China Railway Lanzhou Bureau Group, which is responsible for the construction management of Dunhuang Railway Co., Ltd.

2. Construction scale

There is the renovation of Jiayuguan Station and the new Jiayuguan Station through the Dacaotan Station. The slope of the existing Lanxin main line K746+480-K750+320 section is softened, and the length of the falling road is 292km, the construction of the line project to consider the combination of eternity, the length of the new line double line 2694km。

Dacaotan Station of Lanxin Railway has added 10 new lines (excluding the main line) through the field;Jiayuguan Station has added a line to the uplink field, with an effective length of 880 metersA set of parallel approaches is added at each end of the uplink field;Both platforms have been converted into high platforms;The passenger car maintenance station was relocated to the same side of the station building as the upper line, with 2 equipment lines, 1 bottom stop line, and 1 temporary repair line.

3. Bidding scope and bid division

Jiayuguan Station of Lanxin Railway and related projects. Including the renovation project of Jiayuguan Station and the new Jiayuguan Station through field project in Dacaotan. Including: land acquisition and demolition, roadbed, bridges and culverts, tracks, communication signal information and disaster monitoring, power and traction power supply, housing construction, other operation and production equipment (water supply and drainage, maintenance, vehicles, stations), large-scale temporary facilities and transition projects.

Bid division: This bidding is divided into 2 bids, the project in front of the station is divided into JYGZG-SG1 bids, and the project behind the station is divided into JYGZG-SG2 bids.

4. Planned duration:548 calendar days, with a planned start date of April 1, 2024 and a planned completion date of September 30, 2025.

*: Railway construction plan (the copyright belongs to the original author, if there is any infringement, please contact to delete).