46 mine managers were dismissed and 35 were transferred to the judiciary!

Mondo Social Updated on 2024-01-31

Since the beginning of this year, the Shanxi Bureau of the State Mine Safety Supervision Bureau has strictly investigated the accident, strictly investigated the responsibility of the relevant responsible persons, resolutely punished illegal acts, and made every effort to prevent and curb mine production safety accidents.

It is understood that up to now, the Shanxi Bureau of the State Mine Safety Supervision Bureau has approved and closed a total of 87 coal mine accidents this year, 2,169 people have been held accountable in accordance with the law, 182 people have been removed or dismissed (including 46 mine managers), 35 people have been transferred to judicial organs (including 3 mine directors), and "joint punishment" has been carried out against 2 coal mines and 2 main persons in charge of coal mines.

Accidents involving danger in larger coal mines shall be investigated and dealt with in accordance with the accidents. In 2023, a total of 78 people will be held accountable for 5 risk-related accidents in Panchengling, Ermugou, Maidizhang, Xiaohuigou, and Shaping, of which 12 people will be held accountable by the coal industry group.

With "zero tolerance", we will seriously investigate and deal with accidents that are concealed, falsely reported, and delayed. In the "big doxxing" work to crack down on the concealment of accidents, a total of 1,500 people were held accountable in accordance with the law, 119 people were removed or dismissed from their posts (including 28 mine managers), and 32 people were transferred to judicial organs (including 2 mine directors).

Establish a working mechanism for accident warnings and interviews. For each accident, a three-dimensional animation and warning education film are produced to analyze the causes, which are distributed free of charge to regulatory departments at all levels and mining enterprises, and do a good job in releasing warning information about typical accidents, and urge all mines to be truly vigilant and prevent accidents. Conduct hierarchical interviews with cities and counties where mine production safety accidents occur, consolidate the responsibilities of the main person in charge, the person in charge and the main person in charge of the mine safety supervision department, and promote the fundamental solution of the problem in all localities.

Typical cases of accidents that have been closed recently are as follows:

1. Datong Coal Mine Group Yangfangkou Mining Co., Ltd. Chengjiagou Coal Mine "8.24" General Mechanical and Electrical Accident Typical Case

At 22:22 on August 24, 2023, a general mechanical and electrical accident occurred at the excavation face of the 52602 return air shunchute return air bypass tunnel of Chengjiagou Coal Mine of Yangfangkou Mining Co., Ltd. of Datong Coal Mine Group, resulting in one death. The leader of the excavation team instructed the support workers to operate the roadheader in violation of regulations, and the cutting head of the roadheader twisted the buried air pick, causing the operator who illegally entered the operation area of the roadheader to drag the air duct and fell into the lower right part of the cutting head of the roadheader, and was strangled to death.

Pursuit of criminal responsibility by the relevant responsible persons:

The team leader of the excavation team was transferred to the judicial authorities for handling the accident due to the failure to carry out safety confirmation before the operation and the illegal command of unlicensed personnel to operate the roadheader to sweep coal.

2.The support worker blindly obeyed the command and operated the roadheader in violation of regulations without the qualification to operate the roadheader, resulting in an accident and was transferred to the judicial authorities for handling according to law.

2. Shanxi Xinzhou Shenda Jinbao Coal Industry ***8.12" typical case of general transportation accidents

At about 13:10 on August 12, 2023, a transportation accident occurred 292m away from the roadway of the 13105 coal transportation measures of Shanxi Xinzhou Shenda Jinbao Coal Industry *** hereinafter referred to as Jinbao Coal Industry, resulting in 1 person killed. When the loader was reversing on a watery ramp to transport materials, the vehicle slid out of control and crushed the workers entering the area to death.

Pursuit of criminal responsibility by the relevant responsible persons:

The loader driver failed to confirm the safety before driving the loader to transport materials, and in the case of no one commanding, illegally reversed the vehicle to transport materials on the watery ramp, and the vehicle rolled and caused the accident to occur, and was transferred to the judicial authorities for handling according to law.

Handling of third-party organizations:

Shanxi Fengshuo Machinery and Equipment Manufacturing Co., Ltd. was delivered to Jinbao Coal Industry for use without testing and inspection after upgrading the loading machine brake system and re-obtaining the safety standard certificate. In accordance with the provisions of Article 99 (2) of the Work Safety Law of the People's Republic of China, Fengshuo Company was fined RMB 50,00000). In accordance with the provisions of the "Implementation Rules for the Review and Issuance of Mining Product Safety Marks" (No. ABGZ-MK-04-2017-01), the relevant departments (units) shall revoke the safety standard certificate of their loaders in accordance with their management authority.

3. Shanxi Fenxi Mining (Group) Co., Ltd. Shuangliu Coal Mine "4.23" General Transportation Accident Typical Case

At about 6:13 on April 23, 2023, a transportation accident occurred in Shuangliu Coal Mine of Shanxi Fenxi Mining (Group) Co., Ltd. (hereinafter referred to as Shuangliu Coal Mine) when discharging materials in the main inclined shaft, resulting in 1 person killed and 3 injured. In the process of transporting materials, the mine takes the squad leader and picks up the hook worker to open the barrier to make it in a normally open state, in the case that the redundancy of the wire rope of the main hoist is too long and there is no tension and stress, the string car loaded with materials rushes into the main inclined shaft along the track from the -3 ° slope point, and the main hoisting wire rope is expanded, and the high-strength ring chain of the mine connected with the hook head is broken, resulting in a sports car;The splash in the process of the sports car grazed the three people in the signal chamber at the bottom of the well, and the scraper conveyor chain and sand thrown by the string car that rushed into the bottom of the well parking lot smashed the safety officer who illegally entered the area to death.

Pursuit of criminal responsibility by the relevant responsible persons:

1.The deputy leader of the Shuangliu Coal Mine Transportation and Moving Team and the hook picker (the person in charge of the scene of the main inclined shaft cutting on duty at the time of the accident) opened the wellhead barrier of the main inclined shaft in violation of regulations, and there was an abnormal situation at the operation site, which was not discovered and stopped in time, and was transferred to the judicial authorities for handling in accordance with the law.

2.When the redundancy of the wire rope of the main hoist was too long, the workers of the Shuangliu Coal Mine transportation team (the dispatching winch signalman on duty at the time of the accident) failed to send a stop signal to the dispatching winch driver in time, violating the first paragraph of the fourth paragraph (2) of Chapter 7 of the "Shuangliu Coal Mine Baijiaye Main Inclined Shaft Transportation Operation Regulations" and Article 8 of the "Shuangliu Coal Mine Winch Signalman Operation Regulations", resulting in the accident and being transferred to the judicial authorities for handling according to law.

3.When the redundancy of the wire rope of the main hoist was too long, the workers of the Shuangliu Coal Mine transportation team (the dispatching winch signalman on duty at the time of the accident) failed to send a stop signal to the dispatching winch driver in time, violating the first paragraph of the fourth paragraph (2) of Chapter 7 of the "Shuangliu Coal Mine Baijiaye Main Inclined Shaft Transportation Operation Regulations" and Article 8 of the "Shuangliu Coal Mine Winch Signalman Operation Regulations", resulting in the accident and being transferred to the judicial authorities for handling according to law.

4. Broccoli Group Jushan Coal Mine ***1·27 "Typical Case of Large Water Disaster Accident".

At about 4:38 on January 27, 2023, the Jushan Coal Mine of Shanxi Orchid Group arranged tunneling ZF1212 lane without eliminating the hidden danger of water hazard accidents in the remining area, and advanced drilling (long exploration) violated the "Coal Mine Safety Regulations", and the shift-by-shift detection (short exploration) violated the operation regulations, and the water accumulation in front was not proven, dangerous tunneling, and the damage to the surrounding rock (coal) by long-term soaking of old empty water and artillery, and the coupling of stope stress and water pressure, 3 The water in the upper part of the coal broke through the coal wall with limited thickness and collapsed into the working face instantly, killing 4 people.

Pursuit of criminal responsibility by the relevant responsible persons:

1.The chairman of the board of directors (mine manager) and the legal representative did not establish and improve the safety production responsibility system of the development team, emphasized production and light safety, compressed the number of water exploration and discharge operations, and did not implement the water exploration and discharge system in place, and agreed to the excavation of ZF1211 lane and ZF1212 lane under the condition that the mining design of ZF121 top coal face was not approved, the surrounding goaf water was not dredged, and the hidden dangers were not eliminatedOn December 29, 2022, Orchid Science and Technology did not stop work in time to eliminate hidden dangers after the design was approved, and did not implement the approval requirements. Late reporting of accidents after accidents. It was transferred to the judicial organs for handling in accordance with law.

2.The deputy general manager of production arranged the excavation of ZF1211 lane and ZF1212 lane in advance under the condition that the mining design of ZF121 top coal face was not approved, the surrounding goaf water was not dredged, and the hidden dangers were not eliminated, and on December 29, 2022, Orchid Science and Technology did not stop work in time to eliminate hidden dangers after the design was approved, and did not implement the approval requirementsThe water exploration and release team is mainly engaged in non-water exploration work, and only one water exploration worker is assigned to the water exploration team each time the water is explored. It was transferred to the judicial organs for handling in accordance with law.

3.The assistant of water prevention and control and the chief of the hydrological and geodesy section determined the advance distance of the last water exploration and discharge borehole of the ZF1212 roadway excavation face to be 10m without authorization, and instructed the hydrological and geodesy department to falsify the acceptance data of water exploration and discharge for a long time and cope with the inspection of the superiors. Take direct responsibility for the occurrence of the accident. It was transferred to the judicial organs for handling in accordance with law.

4.The chief engineer was negligent in the management and dereliction of duty in the prevention and control of water, did not grasp the situation of the long exploration of ZF1212 lane on January 19, did not sign the "Notice of Permission to Excavate" after water exploration, and knew that the excavation operation of ZF1212 lane had been carried out on January 24, and did not take measures to stop it;For a long time, there have been problems such as the lack of long-term exploration, the falsification of long-term exploration data, and the issuance of the "Mining Permit Notice" in violation of regulations, and the responsibility for the exploration and release of water in the mine has been out of control at all levels, and the water prevention and control measures have not been implemented. The hydrogeology and old empty water within the well field are not well understood, and the review of the survey report of hidden disaster-causing geological factors, the ground geophysical prospecting report and the management report of the "three zones" prepared by the 114 Exploration Institute is not strict. It was transferred to the judicial organs for handling in accordance with law.

5.The deputy safety captain of the development team was derelict in his duties, failed to perform his duties of supervision and inspection in accordance with the relevant regulations, failed to supervise the on-site personnel of the ZF1212 roadway excavation face to conduct short exploration, and failed to stop the illegal operation of the operators of the ZF1212 excavation face, resulting in the occurrence of water permeability accidents. It was transferred to the judicial organs for handling in accordance with law.

6.The captain of the development team did not have enough education and training for the staff of the team, did not implement the relevant regulations, ignored the relevant requirements of the "Notice of Hydrological and Geodesy" (January 4, 2023), and did not implement the short-term exploration system, and the ZF1212 excavation face carried out the last short-term exploration on the morning shift on the 25thOn the morning of the 26th, the short probe only probed a top eye, and the six shifts of the working face did not carry out short probe in accordance with the regulations, of which 5 shifts did not carry out short probe, and still acquiesced in the on-site organization of production, illegal command, risky operations and other behaviors. It was transferred to the judicial organs for handling in accordance with law.

7.The technician of the Hydrological and Geodesy Department violated the relevant regulations by failing to conduct geophysical prospecting at 70m of the excavation face of ZF1212 Lane on January 2, 2023, and issued a false report on the geophysical prospecting results. On January 19, 2023, the last advance release was not organized. In order to cope with the inspection by the superiors, according to the instructions of the section chief and deputy section chief, false drilling data were fabricated for a long time to cover up the fact that the water exploration and discharge work was not in place. It was transferred to the judicial organs for handling in accordance with law.

8.The deputy general manager of safety did not perform the duties of safety supervision and inspection, and did not stop the illegal excavation of ZF1212 lane on the hidden danger of water hazards and the long-term existence of long and short exploration work is not in place, and the work guidance and supervision of the safety department are not effective, the requirements are not strict, and the investigation and management of hidden dangers are not deep. It was transferred to the judicial organs for handling in accordance with law.

9.The secretary of the Party branch and the captain of the water exploration and release team did not perform the relevant safety production duties, did not attach importance to the water exploration work, and arranged the deputy captain of the water exploration and release team to be fully responsible for the water exploration work, and mainly focused on the work of moving houses and turning noodles and coal mining in the team. After taking office, only 1 water prospector is arranged to carry 3 water prospector positioning cards at will, the team has 96 people on the register, only 12 people hold water exploration qualification certificates, and only 5 water exploration workers are engaged in water exploration work, and the cadres who do not arrange water exploration cadres to follow the scene are not arranged, and the management of the water exploration team is chaotic. It was transferred to the judicial organs for handling in accordance with law.

10.The staff of the Geological Research Center of the 114 Exploration Institute, as the specific undertaker of the "Survey Report on the Hidden Geological Factors Causing Disasters in Jushan Coal Mine", violated the relevant regulations and made the conclusion that "the mining scope of Jushan Coal Mine in the next three years will not be affected by the water accumulation in the goaf" when it was found that there was water accumulation in the goaf in the north wing of the No. 3 coal mining area after going down the mine, and the conclusion of the report was seriously inaccurate. It was transferred to the judicial organs for handling in accordance with law.

11.The staff of the Geological Research Center of the 114 Exploration Institute did not correctly perform their compilation duties, and violated the relevant regulations when compiling the "Survey Report on the Hidden Disaster-causing Geological Factors of the Jushan Coal Mine *** Coal Mine of Shanxi Orchid Group", did not take into account the impact of heavy rainfall on the goaf of Jushan Coal Mine in 2021, misquoted the hydrogeological data of Jushan Coal Mine before October 2021, and found that there was water accumulation in the goaf in the north wing of the 3 coal mining area after going down the mine. Jushan Coal Mine will not be affected by water accumulation in the goaf within the mining scope in the next three years";In the preparation of the "Shanxi Orchid Group Jushan Coal Mine *** Coal Mine Water Prevention and Control "Three Zones" Management Report, deliberately avoided the water accumulation in the goaf of the north wing of the first coal mining area, and divided the north wing of the first mining area into a mineable area (including the ZF1212 roadway excavation face of this accident), and the conclusion of the report was seriously inaccurate. It was transferred to the judicial organs for handling in accordance with law.

Handling of third-party organizations:

1.The 114 Investigation Institute issued a report that was materially inaccurate, and in accordance with the provisions of Article 92, Paragraph 1 of the "Work Safety Law of the People's Republic of China", ordered the 114 Investigation Institute to suspend business for 30 days for rectification, and imposed a fine of RMB 100,00000).

2.In accordance with the provisions of Article 92, Paragraph 1 of the Work Safety Law of the People's Republic of China, Xinbaotong Company was ordered to suspend business for 30 days for rectification and fined RMB 100,00000).

The above content is provided by the Accident Investigation Department of the Shanxi Bureau of the State Mine Safety Supervision Bureau).

* State Mine Safety Supervision Bureau, China Coal NewsAuthor: Li Lun, Niu Xiang.