Case Practice: Automatic batch detection of power distribution terminals, distribution network joint

Mondo Technology Updated on 2024-02-20

Test items: full inspection items of XX Electric Power Research Institute.

Test object: BF2 feeder terminal (standard three-remote FTU, no circuit breaker in the field, use the test platform to collect the trip outlet switch, and upload the fault information to the platform simulation master station through remote signaling and telemetry)HDTS-4000 is an automatic testing platform for power distribution terminals

HDTS-4000 is an automatic testing platform for power distribution terminals

BF2 feeder terminal 1

Test wiring

1) View the aerial illustration definition diagram of the FTU panel; 2) FTU communication network port connection platform switch network port, FTU standard 26 route aviation ** into the platform behind the flight socket;

3) Voltage aviation plug-in external platform terminal block;

4) Open the debugging software of the feeder terminal manufacturer to check the FTU fixed value.

Instructions

The main operation interface of the software.

Communication Configuration:According to the field configuration information, the local IP address is set to 192168.1.1. The terminal debug IP is set to 192168.1.254。Experimental Configuration:1) Enter the project management interface and create a new item.

2) Check the test items according to the test needs.

3) The parameter settings are all FTU fixed parameters, and the actual FTU parameters on site are filled.

4) Point table configuration: Match the point number set inside the FTU with the point number of the test platform. The dot number of the tester is a standard hexadecimal code (4001h of telemetry represents telemetry point number 1, remote signal point number 0001h represents remote signal point number 1, and remote control 6001h represents remote control point number 1).

Configuration of telemetry point table (remote signaling, remote control point table and so on).

5) Enter the distribution network test interface, click Import, open the configuration project, and select "projectsysfig".sys”。Click Open, Scan, and scan the FTU panel with a scanner*** Wait for the device model to be coded, and click Save. 6) Set the terminal IP (the terminal IP of this test is 192.)168.1.254), click the parameter to save, wait for the yellow light below to flash, and the interface terminal and the master station have packet transmission, which means that the tester and FTU communication are successful.

7) Enter the performance interface to increase the amount or manually open and close, and then enter the monitoring interface to monitor the real-time status and displacement of FTU remote signaling, telemetry, and remote control. (This operation can manually verify whether the three-remote test is successful and whether the relevant configuration is correct).

8) Click to enter the detection to enter the automatic detection program.

9) After the test is completed, the program stops and the report is automatically saved.

Test report. This time,Wuhan Halma PowerCooperate with the on-site commissioning personnel of the power supply company to carry out the commissioning of the distribution terminal of the full inspection project of the Electric Power Research Institute, and test 6 terminals at the same time in one operation for no more than 20 minutes, which greatly improves the test efficiency. The staff of the power supply company was very satisfied with the test, saying that after the test, the defect rate of the distribution terminal was further reduced, the practical level of distribution automation was improved, and the stability, safety and reliability of the power supply in the later stage were provided.