Guangxi News, February 3 (Huang Zhenguang) "Your unit insists on stressing politics and taking the overall situation into account, taking the construction of the Pinglu Canal as the top priority, and has carried out a lot of work around the relocation and transformation of the project's communication poles and lines, and has achieved remarkable results, which fully reflects your unit's overall awareness and political responsibility for serving and guaranteeing the construction of the Pinglu Canal." "On the eve of New Year's Day in 2024, Pinglu Canal Group*** wrote a letter of thanks to China Telecom Guangxi, speaking highly of the support and cooperation of the information and communication industry in the region, including the latter.
Telecom construction personnel dismantle and relocate base station equipment. Photo courtesy of Guangxi Telecom.
24-hour construction.
Recently, the reporter came to the construction site of the Pinglu Canal of the Century Project.
Standing on the observation deck of the Qishi Hub Project, one of the three major hubs of the Pinglu Canal, I saw that on the broad construction site, the eight-character billboard with the book "Century Project, Pinglu Canal" stood during the period, and the sixteen characters of the big billboard "through the river to the sea, overall planning, once completed, and system operation" summarized the construction, planning and operation ideas of the project. Tower cranes are lined up, machines are roaring, hook machines are digging hard, transport vehicles are flowing endlessly, and the whole construction site is a busy scene.
Here is 24-hour all-weather construction, people are rotated, and equipment is non-stop. Feng Haibo, deputy general manager of the on-site integrated maintenance center of China Telecom Guangxi Qinzhou Branch, said.
The Pinglu Canal is the first canal built in China for more than 1,000 years since the Beijing-Hangzhou Grand Canal, and is a section of the "four vertical" Hanxianggui water transport channel in the overall layout of China's high-grade shipping planning "four vertical, four horizontal and two networks", and is the backbone project of the new land-sea channel in the west, with a total investment of 727300 million yuan, with a total length of about 134 kilometers, built according to the standard of inland waterways, can be navigated by 5,000-ton ships. 2
Telecom construction workers are reinforcing the temporarily relocated cross-river optical cable poles. Photo courtesy of Guangxi Telecom.
The relocation of communications has run out of "telecommunication speed".
The width of the Pinglu Canal is between 180 meters and 220 meters, the project is large, the number of communication facilities that need to be relocated within the construction red line is large, involving four basic telecommunications operators, about 6,424 kilometers of communication lines are demolished, and 7,884 kilometers are newly built. In October 2023, the Canal Group proposed that the relocation and transformation of the communication pipeline should be completed by the end of that year, and the time is tight and the task is heavy.
The relocation and reconstruction project involving the telecommunications company includes 1,226 poles and 53 hanging wires81 km, 0 new pipelines85 km, 3,046 km of new fiber optic cables and 2,117 km of dismantled fiber optic cables. Except for a small number of projects in Nanning, they are mainly distributed in Qinzhou City. Li Zhenqiang, director of the cloud network operation department of China Telecom Guangxi, introduced.
Lai Guojun, deputy general manager of China Telecom Qinzhou Branch, told reporters that such a quantity of work, according to the normal construction force of the branch, it is difficult to complete within a year, and Zhang Li, deputy general manager of Guangxi Company, led a team to the site to investigate, and upgraded the project to the control project of Guangxi Company, requiring the cloud network operation department to take the lead in coordinating and organizing the communication design, construction and supervision of all aspects of the work, and mobilized more than 10 construction teams from the whole region to support, racing against time to seize the progress, to ensure the completion of the task.
The Canal Group, the Communications Administration of the Autonomous Region and the telecommunications enterprises have established a joint mechanism for the relocation and reform of telecommunications, held regular consultations, and in line with the construction principle of sub-sectional contracting, joint construction and sharing, inverted schedules, wall charts, broken card points, and dredged blockages, which greatly improved the efficiency of the relocation and reform work, and ensured that the people's communications were not affected, and basically completed the relocation and transformation of the waterway section of the pipeline 10 days ahead of schedule on December 20 last year, and strongly supported the construction of the canal project. **, deputy general manager of the cloud network operation department of China Telecom Guangxi, said.
The canal's communication support has not been slackened at all.
Feng Haibo introduced that just after New Year's Day, Wang Zhifang, general manager of China Telecom Guangxi, came to the construction site of the Pinglu Canal horse road hub and communication line relocation and transformation to investigate, emphasizing that supporting the construction of the canal is a major political task, and it is necessary to effectively improve the political position, keep an eye on the progress of the canal project, pay attention to the follow-up relocation and transformation work, take the initiative, plan ahead, fully support the construction of the service canal, tighten the responsibility for safe production, and ensure the efficient and safe implementation of the relocation and transformation project.
In the relocation of Qingsong Village, Jiuzhou Town, in the face of the reporter's question of whether it can be slowed down now, Feng Haibo shook his head again and again, "This is a new transitional pole road, which is the direction of the word '7', across the village road, General Manager Wang Zhifang asked to change the single pole to H pole during the on-site investigation, and add an electric pole at the turn of the road to ensure safety." ”
According to Feng Haibo, there are still three tasks in the current relocation and reform work. First, on the basis of completing the phased relocation and reform tasks in the early stage, in accordance with the management and control requirements of Guangxi Company, we will continue to do a good job in project progress, quality, safety and investment control, and create high-quality projects, "clean projects" and safety projects; Second, for individual sites and poles that do not affect the construction of the canal project in the early stage and have not yet been relocated, the relocation or demolition shall be completed in a timely manner according to the progress of the canal project; The third is to carry out an inventory of the pole roads and pipeline resources around the five bridge projects in the waterway of Qinzhou City, so as to quickly complete the temporary relocation and modification of communication lines before the construction of the canal bridge and ensure that it is important.
The security migration of the primary and secondary communication trunk lines and metropolitan area networks ensures that the communication of the party, government, military and customers will not be affected. In addition, part of the cross-canal river line is temporarily relocated, and after the completion of the construction of the river hub and bridge, it needs to be relocated to the permanent route across the river, which is a task to be updated with the continuous progress of the follow-up project of the canal. (ENDS).