On the occasion of the Spring Festival and reunion, the Zhangzhou nuclear power project in Yunxiao County did not stop, and more than 2,000 "nuclear industry people" were stationed on the front line to build a dream of "a great power".
During the Spring Festival, nuclear power builders stuck to their posts and did a good job in equipment commissioning.
During the Spring Festival, our main task is to do a good job in eliminating the shortage of the nuclear island system, so as to lay a solid foundation for the safe and smooth development of the hot test work after the holiday. Yuan Hangwei, commissioning engineer of the commissioning and production preparation department of China Nuclear Guodian Zhangzhou Energy, introduced. In 2024, Zhangzhou Nuclear Power Unit 1 will be officially put into operation for power generation, and the hot test operation after the Spring Festival is crucial. In order to ensure the smooth progress of various nodes, Yuan Hangwei and his colleagues chose to celebrate the New Year on the spot and contribute to the construction of 100 billion clean energy projects.
Also sticking to their posts are the operators of the main control room of Unit 1. "The main control room is the brain of the unit, and the operation of important equipment must be closely monitored 24 hours a day. We have a heavy responsibility on our shoulders and a glorious mission, and we will resolutely stand on the first shift of the Year of the Dragon to escort the construction of the unit. Mao Wenhai, the night shift reserve director of the operation department of Zhangzhou Energy Company, said.
In the factory area, there are night lights. On the construction site, it was a busy scene. During the Spring Festival this year, more than 500 builders of CNNC No. 24 Company stayed behind for the construction, making full preparations for the partial work delivery of Unit 2 and the start of the FCD of Unit 3 after the New Year, and infiltrating the New Year with hard sweat.
The construction of central enterprise projects is "not closed", and the local service guarantee is "not degraded". According to the "Zhang's 12 Measures", Yunxiao County continued to consolidate and expand the joint mechanism of government and enterprises for nuclear power projects, continuously deepened communication and docking, strengthened factor guarantees, strengthened policy publicity, and did a good job of condolences and care, so as to escort the construction of major projects, so that front-line builders feel at home and at home, and the government and enterprises worked together to ensure a "good start" for the industry in the first quarter.
The main leaders of the county party committee and county ** came to the factory to make dumplings and eat Chinese New Year's Eve dinner with us, sending us blessings and boosting morale, and the company also arranged a lot of ceremonial New Year activities, so that we could celebrate a good year in the clouds and celebrate the new year, without distractions to promote the project. Yu Rongjian, the director of the main control room, said.
The total investment of Zhangzhou nuclear power project exceeds 100 billion yuan, and it is planned to build 6 + 2 "Hualong No. 1" nuclear power units, after the project is completed, the annual power generation is expected to be 72 billion kilowatt hours, which is of great significance to China's transformation from a nuclear power country to a nuclear power power.