Capped next month! These buildings of Jinbang Primary School will be completed by the end of August

Mondo Social Updated on 2024-03-08

Recently, the construction progress of the Jinbang Primary School project in Yudong New District has been accelerated, and the 1 office complex building and 5 teaching buildings have been built to the height of one floor, and the construction of the entire project has made new progress. The construction site of the project is in full swing, the tower crane shuttles back and forth to transport the steel bar materials, and the workers are busy processing the binding steel bars, building templates, etc., to prepare for pouring concrete; At the stadium site, bulldozers and excavators roar to level the land.

Workers are tying up rebar.

Workers level the concrete surface of the roof.

At present, the main construction of the project is mainly carried out, and there are more than 150 on-site construction personnel. Ou Guanglin, executive manager of the Jinbang Primary School Project in Yudong New District, CCCC First Harbor Bureau, introduced that affected by the relocation of high-voltage lines in the site, the Jinbang Primary School project will be constructed in two stages, according to the overall construction schedule, the first stage is before the end of August 2024, and the construction of 1 office complex and 2 teaching buildings that will not be affected by the relocation of high-voltage lines will be completed, and the conditions for handover and use will be met. The second phase is to complete the construction of the remaining 3 teaching buildings, 8 gymnasiums and corresponding outdoor supporting facilities by September 2025 after the relocation of the high-voltage lines.

Project construction site.

Up to now, the pouring of the roof of the first floor of the 1st comprehensive building of Jinbang Primary School has been completed; 2. The first floor of the teaching building is undergoing steel bar binding construction, which is currently 60% complete; 4. The installation of the roof formwork on the first floor of the teaching building is 90% completed; 5. The reinforcement binding construction of the roof on the second floor of the teaching building is 85% completed, and the construction of earthwork backfill is underway in the sports field. "The four buildings that started construction in advance are scheduled to be topped out in late April this year. Ou Guanglin introduced that the next step of the project will continue to increase investment in personnel and equipment to ensure that the construction task is completed on time and with good quality. According to the design, the total investment of Jinbang Primary School in Yudong New District is 20.6 billion yuan, with a planned total land area of more than 100 acres and 3,000 degrees. The project is located on the north side of the intersection of Jinbang Road and Chaoxia Road, Yudong New District, Yulin City, with a total construction area of about 4140,000 square meters, the main construction content includes 1 office building, 6 teaching buildings, 1 gymnasium building, 11 independent wind and rain corridors and supporting facilities. After the completion of the project, it will effectively fill the gap of primary school places in the region, provide a strong guarantee for school-age children's enrollment, and improve the quality of compulsory education in the region.

Related Pages