Preface. The speed of China's infrastructure construction is well-known all over the world, and it is also known as the "infrastructure madness".
If you want to build a hospital that can accommodate more than 1,600 people and cover an area of nearly 80,000 square meters, how long will it take?
Some people may say that it will take at least three or five years.
If it is said that a hospital can be built in 12 days, some people must think that it is bragging and an impossible task.
But our workers successfully completed the task, and two days later, it was delivered.
That is Leishenshan Hospital in Wuhan.
Now that 4 years have passed, is Leishenshan Hospital still in use? What is the current state of the hospital?
High-rise buildings rise from the ground.
At the beginning of 2020, the Lunar New Year was approaching, but what people did not expect was that a virus that threatened all of humanity began to spread silently.
And the virus has also been carried to all parts of the country with the movement of people.
The most affected place is Wuhan.
At that time, Wuhan's medical resources were under great pressure, and doctors from all over the country volunteered to come to support.
Such a scene is tearful, and truly embodies what it means to "support from all sides when one side is in trouble".
The hospital was also very short of beds, so under the severe situation at that time, it was decided to build a temporary hospital to accommodate patients.
At this time, time is of the essence, and every minute and second is precious.
The site selection and design of the hospital was completed in less than a day.
Because there are precedents of Huoshenshan Hospital and Beijing Xiaotangshan Hospital, the design plan is still very fast.
On January 27th, Leishenshan Hospital officially started.
In total, nearly 20,000 construction workers joined the construction of the hospital, and the construction speed is very fast.
In just 12 days, it was built, and on February 6, it was officially handed over to the military management.
It can be said that this speed has surprised many people, and it is a real flat sky.
Not only that, but the design of the hospital is also quite reasonable, including a variety of functions to meet all the needs of doctors and patients.
But when it was built, there were also a lot of difficulties, which can also be said to be twists and turns.
First of all, the most important thing is the construction personnel, and if you want to build a hospital in a short time, it means that you need a lot of workers.
But at that time, it was the time of the Spring Festival, and many workers also returned to their hometowns for the New Year, and they couldn't find so many manpower for a while.
Therefore, an urgent recruitment announcement was also issued.
After receiving the news, countless construction workers said goodbye to their families and resolutely went to Wuhan to build a hospital.
Soon, more than 30,000 construction workers arrived at Leishenshan Hospital one after another.
In order to ensure that the hospital can be delivered within the specified time, a two-shift working mode was designed during the construction of Leishenshan.
Even at night, the Leishenshan Hospital is brightly lit, and some workers simply rest for a few hours before getting up to work again.
Similarly, in order to make the construction of the hospital more reasonable, the designers did not dare to rest, and used the "black technology" - BIM technology.
To put it simply, it is to use computer computing to design an architectural model, so that many problems can be avoided in actual construction.
Even if a problem is discovered, it can be corrected quickly.
At that time, the situation was constantly changing every day, and the initial plan was to build a floor area of 50,000 square meters.
However, the so-called plan could not keep up with the changes, hoping to accommodate more patients, so by the time of completion, the area of Leishenshan Hospital had reached nearly 80,000 square meters.
The main reason why the construction area can continue to expand is that the design at that time was very ingenious.
It adopts the "I" shaped building structure.
Therefore, it is very convenient to extend and expand such a structure from any direction, and it will not affect the structure of the main body at all.
Again, this design structure is not simply for the convenience of expansion.
Another important reason is that the doctor's area and the patient's area are completely separated.
This means that the chance of cross-infection between doctors and patients is greatly reduced.
Therefore, in Leishenshan Hospital, the myth that no staff member was infected was also created.
At that time, there were nearly 3,000 medical workers working in Leishenshan.
But by the time the hospital was closed, no one was infected.
This is not only due to the strict protection and disinfection work of people at that time, but also has a lot to do with the construction structure of Leishen Mountain.
At the same time, Leishenshan Hospital is also a very modern and high-tech hospital.
When the hospital was built, the use of modern information technology was taken into account for the monitoring and management of the hospital.
There is an advanced information management center that analyzes the patient's condition, which not only improves the efficiency of medical treatment, but also provides a lot of useful data for prevention.
It can be said that it is really a miracle to be able to build such a reasonable hospital in 12 days, integrating modernization and information intelligence systems.
What is the current status of Leishenshan Hospital?
On April 14th, all patients were discharged, which means that Leishenshan Hospital has also fulfilled its mission.
On the 15th, the hospital was completely disinfected and the hospital gate was closed.
From delivery to closure, 2 months and 8 days passed, during which a total of 2,011 patients were admitted, and 1,900 patients were finally cured and discharged.
Although the mission of Leishenshan Hospital has been completed, the touching it brought to us at that time will remain in our hearts forever.
Now, 4 years have passed, and Leishenshan Hospital is still standing there, and it has not been demolished, but it has not continued to be put into use.
After all, it was only used as a temporary place to store patients, so after the last patient left, it meant that it would retire from the stage of history.
However, Xiaotangshan Hospital, which made outstanding contributions during the SARS period, also began to be rebuilt in 2020, and now it has become a first-class general hospital.
Therefore, there is a precedent, and I believe that Leishenshan Hospital will play a role one day.
Text |On Yunxuan.
Edit |On Yunxuan.
Reference: The Paper News - "Science and Technology Innovation Power丨Science and Technology Support to Create a Miracle in the Construction of Huoshenshan Leishenshan Hospital".
Guangming Network - Leishenshan Hospital is cleared! Let's review the amazing "impossible" of TA