Municipal engineering.
1.1. Special protection measures for construction sites and adjacent buildings, structures and underground pipelines.
1.1.1. The project management center provides the project department with the transfer of above-ground and underground pipeline data and adjacent buildings, structures and underground engineering materials on the construction site and adjacent areas.
1.1.2. Before the start of construction, the project department shall formulate special protection measures for adjacent buildings, structures and underground pipelines, and report to the chief engineer for approval.
1.2. Verify the subcontractor's enterprise qualification and safety production license, and sign a safety agreement with the subcontractor.
1.2.1. Verify the subcontractor's enterprise qualification and safety production license before the project starts, and sign a safety agreement with the subcontractor.
1.2.2. The main content and requirements of verification.
1) The subcontractor shall have the corresponding qualifications and shall hold a valid safety production license.
2) The subcontract and safety agreement shall be concluded before the construction of the subcontracted project, and the safety responsibilities, rights and obligations of both parties shall comply with the provisions of the safety law, and there shall be no exemption clause.
1.3. Formulate safety technical measures in the construction organization design
1.3.1. Formulate safety technical measures in the construction organization design and report to the supervision engineer for review.
1.3.2. To formulate safety technical measures in the construction organization design, we should pay attention to the following:
1) The content of safety technical measures should comply with the mandatory standards for engineering construction;Technical measures or special construction plans for green construction should be prepared.
2) should be prepared a list of dangerous sub-projects and the corresponding special construction plan, and in line with the relevant regulations;If it is prepared in stages, there should be a preparation plan;
3) Preparation of emergency plans for production safety accidents;
4) The formulation of seasonal safety construction plans such as winter and rainy seasons should meet the requirements of the specification;
5) The general layout of the construction should meet the requirements of safety and fire protection.
1.4. Prepare a special construction plan for the sub-project with greater risk
1.4.1. Prepare a special construction plan for the sub-project with greater risk and submit it to the supervising engineer for review.
1.4.2. The preparation and review of the special construction plan should pay attention to the following:
1) The content of the special construction plan shall comply with the mandatory standards for engineering construction;
2) If the construction method and construction sequence have been clarified in the construction design, the special construction plan should be in line with the design;
3) If expert argumentation should be organized, there is a written argumentation review report by experts, and the signature of the argumentation review report is complete and valid
4) The special construction plan should be improved according to the concluding opinions put forward in the expert argumentation review report.
1.5. Establish and improve the safety production guarantee system on the construction site
1.5.1. Establish and improve the safety production guarantee system on the construction site, and report to the supervision engineer for review.
1.5.2. The establishment of the safety production guarantee system on the construction site shall comply with the following contents:
1) The establishment of the safety production management organization of the project department shall comply with the relevant regulations;The safety management objectives should be clear and in accordance with the contract;
2) Establish and improve the construction safety production responsibility system, safety inspection system and accident reporting system;
3) The professional qualification certificate and safety production assessment certificate of the person in charge of the project department should be complete and validThe person in charge of the subcontracting team shall have the corresponding professional qualification certificate and safety production assessment certificate;
4) The number of full-time safety production management personnel should be in line with the provisions of the Measures for the Establishment of Safety Production Management Institutions and the Allocation of Full-time Safety Production Management Personnel in Construction Enterprises (Jianzhi [2008] No. 91), and their professional qualification certificates and safety production assessment certificates should be complete and valid.
If the number of construction personnel in the labor subcontracting team is less than 50, one full-time safety production management personnel shall be appointed;50,200 people, 2 full-time safety production management personnel shall be appointed;More than 200 people, set up 3 full-time safety production management personnel, and according to the actual situation of the construction of the sub-project construction hazard, shall not be less than 5 of the total number of engineering construction personnel.
The professional subcontracting team shall set up full-time safety production management personnel according to the quantity or cost of the subcontracted project.
1.6. Pay attention to the safety education and training of on-site personnel and make training records
1.6.1. Safety education and training should be carried out for on-site personnel and training records should be made.
1.6.2. Safety education and training mainly include the following contents.
1) Before the start of the project, carry out safety education for the personnel entering the site, including the following main contents:
* The content of education should include safety regulations, safety management system of the construction project department, common sense of safety production and safety operation procedures for relevant types of work and equipment, and written notification of dangerous parts to operators in dangerous positions, relevant operating procedures and hazards of illegal operations**Education should be gradually deepened, and team education must be carried out in combination with the actual situation of the operating environment and homework content.
* The coverage of education should be 100, and the education records should be complete, and the education time, teaching personnel, education content, and personnel receiving education should be recordedAll persons receiving education should sign for confirmation. Keep the test papers.
2) Safety production education and training should be carried out at least once a year for managers and operators, and the education and training should be recorded in personal work files.
3) Before the operator enters a new position or a new construction site, safety production education and training should be carried out. Personnel who have not received education and training or who fail to pass the education and training assessment shall not be allowed to work.
4) When adopting new technologies, new processes, new equipment and new materials, corresponding safety production education and training should be carried out for operators.