Brick masonry No. 010401 .

Mondo Social Updated on 2024-02-01

Masonry works include brick masonry, block masonry, stone masonry, and cushion.

Brick masonry includes brick foundation, brick digging pile retaining wall, solid brick wall, perforated brick wall, hollow brick wall, hollow bucket wall, hollow flower wall, infill wall, solid brick column, perforated brick column, brick inspection well, sporadic bricklaying, brick scattered water (floor), brick trench (open ditch).

The division of the foundation and the wall (column).: The foundation and the wall (column) body are usedThe same materialtime, toDesign interior floors as boundaries(If there is a basement, the basement interior design ground is the boundary), the following is the foundation, and the above is the wall (column) body. Foundation and wall usedifferent materialstime,When the height of the floor in the design room is less than or equal to 300mm, different materials are used as the dividing line, and when the height is greater than 300mm, the design indoor floor is used as the dividing line. The brick fence should be bounded by the design outdoor floor, with the following as the foundation and the above as the wall

1.Quantity calculation rules

Table 53.11 Standard brick wall thickness table

2.Related Notes:

1) Brick masonry joints are listed according to the "wall joints" project code in the wall plastering, and the solid brick walls, perforated brick walls, hollow brick walls and other projects do not include the joints, including scraping joints. The reinforcement of steel bars in the brick masonry, the ladder in the inspection well, and the concrete components in the well should be listed according to the relevant item codes in the "concrete and reinforced concrete engineering".

2) The chimney, ventilation duct and garbage chute attached to the wall should be calculated by volume (deducting the volume occupied by the hole) according to the size shown in the design drawingIncorporationwithin the volume of the wall to which it is attached. When the design stipulates that the hole needs to be plastered, it should be coded according to the sporadic plastering items in the "wall, column decoration and partition, curtain wall project".