InstallationHydrogen bellows globe valve WJ15F16pSteps:
1.Clean valves and pipes: Before installation, valves and pipes need to be cleaned to ensure that there are no impurities or dirt.
2.Check the size of the pipe: Make sure that the size of the pipe matches the valve and that the inside of the pipe is smooth and spine.
3.Lubrication of the seat and packing: Lubricate the sealing surface and packing of the seat with lubricant to ensure a good seal and reduce friction.
4.Place the valve into the pipe: Place the valve gently into the pipe, making sure it is in the right direction and that there are no bumps or scratches.
5.Secure the valve: Use a wrench and screwdriver to secure the valve in the pipe, making sure it is stable and does not come loose.
6.Test the valve: After the installation is complete, a test is performed to ensure that the valve is working properly and that there are no leaks.
7.Record installation information: record important information during the installation process, such as the position, direction, fixing method of the valve, etc., so as to facilitate subsequent maintenance and management.
Precautions: When installing the bellows shut-off valve, the following matters need to be noted:
1.Follow the manufacturer's installation guidelines and follow the prescribed steps.
2.During installation, avoid excessive force or use of inappropriate tools to avoid damage to valves or pipes.
3.Before testing the valve, make sure all bolts and nuts are tightened.