Sampling location]: Dormitory of the University of Finance.
Construction Update]: Carpentry completed.
Gypsum board seals, it is forbidden to splice them with small pieces.
The top is required to be fixed with expansion bolts.
The surface layer at the 90° corner of the gypsum board needs to be L-shaped.
The gypsum board sealing board requires that the joints are V-shaped openings of about 5mm.
Sampling location]: Nursery community spring.
Construction Update]: Oilman inspection.
Brush the primer after sanding.
Brush the topcoat.
Repeat the topcoat twice.
Acceptance criteria before painting:
1. After the top angle line plaster is leveled, the baseboard putty is scraped to the ground, and the 2 meters are detected by a ruler of 2 mm.
2. The yin and yang angles need to be embedded with right-angle strips, the yang angles are vertical, and the straightening error of the yin angles is 1Within 5 mm.
3. All slotted places and seams are treated with grid and kraft paper.
4. Door covers, window covers, and passes, horizontal and vertical lines need to be made.
Sampling location]: MCC Liyuan.
Construction Update]: Groundbreaking Ceremony.
Groundbreaking Ceremony Preparations:
Banners, hammers, tables, red tablecloths, red carpets, drinks, salutes, fire extinguishers, responsibility supervision signs, safety signs.
Safety signs: play the role of safety precautions, standardize the material placement area, reduce the occurrence of safety accidents and ensure that the on-site materials are placed in a neat and orderly manner.