35kV two core heat shrinkable cable head production steps

Mondo Social Updated on 2024-01-31

The steps to make a 35kV two-core heat shrinkable cable head are as follows:

1.Prepare tools and materials: including cable headers, heat shrink tubing, cable terminations, cable glands, cable tape, cable pliers, cable scissors, etc.

2.Clean the cable header: Use cable pliers and cable scissors to clean the cable head and make sure the surface of the cable head is clean, dust-free, and oil-free.

3.Install the cable termination: Place the cable termination on the cable head, making sure that the cable termination fits snugly with the cable head.

4.Install the cable gland: Place the cable gland over the cable termination, making sure the cable gland fits snugly against the cable termination.

5.Install the heat shrink tubing: Cover the heat shrink tubing over the cable glands to ensure that the heat shrink tubing fits snugly with the cable glands.

6.Heat shrinkable cable head: Use a heat shrink machine to heat shrink the heat shrinkable tube to ensure that the heat shrinkable tube and the cable joint fit tightly to form a good insulation effect.

7.Check the cable head: Check whether the cable head is installed correctly, whether there is leakage, short circuit, etc.

8.Complete the cable head fabrication: After completing the cable head fabrication, use cable tape to fix the cable head on the cable to ensure that the cable head fits tightly with the cable.

The above is the steps of making a 35kv two-core heat shrinkable cable head, it should be noted that in the process of making the cable head, it must be ensured that the installation of the cable head is correct to ensure the insulation effect and safety of the cable.